CAUGHT IN THE MIDDLE
New Mexico bridge case highlights the importance of written agreements for changes and delay compensation

In construction contracting, hope for (and focus on) the best after planning for the worst.

In 2018, the New Mexico Department of Transportation (NMDOT) selected a prime contractor for construction of a bridge in Quay County, N.M. (The eastern border of Quay County is also the New Mexico/Texas border). The prime subcontracted for cast-in-place piers and other bridge components. NMDOT and the prime entered into a change order to alter the pier design, which increased the quantity of work and delayed the project. Continue reading.

Published On: August 26, 2025

Share This Story, Choose Your Platform!

Government Liability for Third-Party Delays

July 18, 2017|

Generally, the Government is not responsible for delays caused by third parties, even other contractors at its own project site, unless the Government affirmatively indicates the site will be ready and available. 

Barbecue and Construction Contracts

June 28, 2017|

While barbecue recipes can be short and simple, contracts can be long and complicated.  Fundamentally, though, recipes are very much like contracts: what’s required, how much of each part/ingredient, in what order should they be assembled/added, when, and for how long?

Show Your Work

June 19, 2017|

A mentor of mine once said that process and procedures can be more important than substance and results.  Like solving a math problem, how you solve it is often more important than the answer itself.  The same is true in resolving construction contract disputes with public owners.

Hide, Seek, & Seek

May 30, 2017|

Have you ever played hide and seek? If you are the seeker, do you win the game when you find the hidden person? Yes, of course! Unless, you’re a government contractor.

Contractor Schooled School

May 22, 2017|

Have you ever done exactly what you were supposed to do, but it didn’t work and you were blamed anyway? Nevertheless, if contractors follow the owner’s plans and it still doesn’t work, the contractor may be without fault – this is as it should be.

Walk It Off, Keep Going

May 15, 2017|

During a recent soccer game, my seven-year-old son took the ball squarely in the face. But, he walked it off and continued playing. Contractors must do the same with changes.

Share This Story, Choose Your Platform!

Jonathan J. Straw
Best Lawyers® - Jonathan Straw | 2026

Share This Story, Choose Your Platform!