Have you ever done exactly what you were supposed to do, but it didn’t work and you were blamed anyway? Nevertheless, if contractors follow the owner’s plans and it still doesn’t work, the contractor may be without fault – this is as it should be.
This happened when a public school district near Cape Girardeau, Missouri provided electrical plans to a contractor for an addition to a local high school. The contractor followed the plans and when problems arose, the school district blamed the contractor. Ultimately, however, the contractor can rely on the accuracy of the plans provided by the school district and the contractor may be blameless.
Contractors, be aware! Your express warranty can overwrite the owner’s implied Spearin warranty. If the contract includes language like “contractor has verified [or guarantees] the accuracy of the plans and specifications,” the contractor may be assuming responsibility for the owner’s design or plans.
Always understand what you’re signing or saying beforehand.
Roads & Bridges | Written Notice
WRITTEN NOTICE | Beware that strict compliance of the contract might be required.
When an owner replaced a contractor for significant safety violations, […]
Roads & Bridges | Mommie Dearest
MOMMY DEAREST | The story of an ESA without a MOM
Nobody enters this world, or a contract, without a mother: There can […]
IIJA | Does Closing a “Giant Loophole” Cost Contractors?
A recent article published by Roads and Bridges magazine reports that the Office of Management and Budget is working to broaden the scope […]
Roads & Bridges | Buy American Plan Gets an Update
BUY AMERICAN PLAN GETS AN UPDATE
The Office of Management and Budget is developing standards to replace the current Buy […]
Roads & Bridges
Where Does the Buck Stop?
WHERE DOES THE BUCK STOP? | A shallow concrete pour leads to an interesting lawsuit
On the desk of President Harry S. Truman […]
Roads & Bridges | Reshaping Agreements
RESHAPING AGREEMENTS | Oral Agreements Must Be Written in Stone
Reuse, reshaping, and/or reapplication of existing materials was the goal in this roadway […]
Pay-If-Paid Unenforceable in Virginia Starting Jan. 1, 2023
As of Jan. 1, 2023, pay-if-paid clauses are unenforceable, regardless of whether a surety/payment bond claim is involved. This is only for […]
How Short is Too Short
A limitations period is too short when it’s unreasonably short.
Construction Contracting Without Relief Clauses During COVID-19
What to do if your contract lacks the parts to handle COVID-19? Considerations for creating new contracts during COVID-19.

Jonathan J. Straw
Blog Author
Contact Jonathan
Partner | KraftsonCaudle.com
Download Jon’s Bio