During a recent soccer game, my seven-year-old son took the ball squarely in the face.  But, he walked it off and continued playing.  Contractors must do the same with changes.

In 2006, under a contract with NAVFAC for repairs to a wastewater treatment system at Naval Station Guantanamo Bay Cuba, the Contractor encountered differing site conditions.  NAVFAC did not issue a suspension or stop work order, but the Contractor stopped working awaiting responses to RFIs.  NAVFAC did not respond to all the RFIs.  So, the Contractor submitted a certified claim, but the Contractor never resumed work.  The Contractor should have continued working.

Under the Federal Acquisition Regulations, the Contractor is obligated to “prosecute the work diligently” and continue performance pending the outcome of a claim. (FAR 52.211-10 and 52.233-1(i)).  Doing so not only mitigates potential delays and damages, but it ensures that when a claim is submitted, a “sum certain” (i.e., showing of damage) is possible.

In this case, the Contractor’s claim submission was premature and the Contractor’s refusal to perform directed or constructive changes pending the promise of payment precluded the ASBCA from having any power to resolve the dispute.  The ASBCA dismissed the Contractor’s appeal because the Contractor sought future damages for work it had not yet performed.  At worst, NAVFAC could have terminated the Contractor for default.

Appeal of Islands Mechanical Contractor, Inc., ASBCA No. 59655 (April 13, 2017)

Published On: May 15, 2017

Share This Story, Choose Your Platform!

  • Sum Certain Blog Post

Jurisdiction is Power

August 27, 2023|

Not bad power, but the ability of a decision-maker (e.g., court) to decide which side is right (or which is more correct). […]

  • Heavy Construction Law | Mediation Melee | Roads & Bridges

Roads & Bridges | Mediation Melee

June 13, 2023|

MEDIATION MELEE| An arbitration case can be costly

Arbitration can be a bridge over troubled waters. In this crossing, the parties argued over […]

  • Written Notice | Roads & Bridges Article | Jon Straw

Roads & Bridges | Written Notice

April 2, 2023|

WRITTEN NOTICE | Beware that strict compliance of the contract might be required.

When an owner replaced a contractor for significant safety violations, […]

Share This Story, Choose Your Platform!