A mentor of mine once said that process and procedures can be more important than substance and results. Like solving a math problem, how you solve it is often more important than the answer itself. The same is true in resolving construction contract disputes with public owners.
Under a contract with the City of Baltimore, the Contractor agreed to complete an administrative dispute resolution process before suing the City. But, without first completing the administrative process, the Contractor sued the City. The Contractor tried to justify its lawsuit by arguing that the City had also agreed to follow an administrative process before it could assess liquidated damages and that the City was the first to breach the contract by not following that administrative process. (Being the first to breach the contract may excuse another party’s later breach of the same contract.)
The Court did not have to decide if the City first breached the contract because the Court decided the Contractor didn’t properly follow the administrative process before suing the City.
The Contractor has not lost the war, but it lost this battle, time, and money. Follow the process even if it appears unnecessary. As a math teacher might say, “show your work.”
Roads & Bridges | Award Upheld in W. Va. Caisson Dispute
AWARD UPHELD IN W.VA. CAISSON DISPUTE
Federal court reinforces high bar for overturning arbitration
In 2018, the West Virginia Department of Highways (DOH) awarded […]
Roads & Bridges |Let the Contract Lead
LET THE CONTRACT LEAD
Documents offer guidance needed to manage risk without derailing projects
Construction is an industry of managed risk. Whether the prices […]
Roads & Bridges | When is an Invoice Really an Invoice?
WHEN IS AN INVOICE REALLY AN INVOICE?
All court decisions are opinions. Appellate court decisions are typically made by a panel of three […]
Roads & Bridges | Clarifying Punitive Damages
CLARIFYING PUNITIVE DAMAGES
In June 2021, the South Dakota Department of Transportation contracted for the demolition and construction of a bridge on State […]
Roads & Bridges | When Approximate Means Assumed Risk
WHEN APPROXIMATE MEANS ASSUMED RISK
A New York Court Shows How Performance Specifications Can Leave Contractors Holding the Bag
Sometimes when we are told […]
Roads & Bridges | From Roman Arches to AI
FROM ROMAN ARCHES TO AI
Can Construction Evolve Without Risk?
The construction industry blends old with new. From ancient Roman archways and aqueducts and […]
Roads & Bridges | Caught in the Middle
CAUGHT IN THE MIDDLE
New Mexico bridge case highlights the importance of written agreements for changes and delay compensation
In construction contracting, hope for […]
Roads & Bridges | Wait and It’s Waived
WAIT AND IT’S WAIVED
Roads & Bridges | Supreme Court Ruling on Arbitration Delay
Don’t wait to arbitrate! Progressing too far down the litigation […]
Roads & Bridges | Court Defines When Contractors Can Withdraw Due to Mistakes
BIDDING BLUNDER
Roads & Bridges | Court Defines When Contractors Can Withdraw Due to Mistakes
For over 125 years, the vast majority of jurisdictions […]










