The White House has directed Agency heads to “terminate or modify . . . covered contracts.” With some exceptions, there are numerous potential contracts on the chopping block. What should contractors do?
Upon receipt of a unilateral modification, assess whether the cost or time will increase in unchanged areas. For example, deductive changes for certain work could increase costs for other work that must still be performed. If costs were increased because of deductive changes, then carefully consider submitting a request for equitable adjustment.
Upon receipt of a notice of complete termination for convenience, promptly stop incurring further costs and, within one year of the termination, present a reasonable and well-supported termination settlement proposal to the Government under FAR 52.249-2(e). Recoverable costs include:
1. Costs actually incurred;
2. Profit on the work actually done; and
3. Costs of preparing a termination settlement proposal.
Upon receipt of a notice of partial termination for convenience, promptly stop incurring costs related to the terminated portion of the work and present a request for equitable adjustment within 90 days of the notice under FAR 52.249-2(l).
HEADER PHOTO: Termination by Nick Youngson CC BY-SA 3.0 Alpha Stock Images
Navigating the Requirements for Claims against Virginia Public Entities
Contractors making claims against Virginia public entities must follow ALL applicable requirements. Such requirements may be found in several places, so check […]
Virginia General Contractors Not Protected from Pre-Work Claim Waivers
On March 2, 2018, the Governor approved an act of the Virginia General Assembly to make unenforceable pre-work waivers of lien rights […]
Adding Terms to a Government Contract without Saying So
Imagine an incredulous Contractor asking, “Show me in the Contract where it says I’m supposed to do X?” The Government Contracting Officer smugly answers, “even though the Contract doesn’t say so, you must do it anyway.” Is that even possible, when, how?
Differing Site Conditions: When the Part Does Not Equal the Whole
If all apples are fruit, then why are all fruit not apples?
Forum Selection Can Be a Home-Court Advantage
I promise that any disputes between us will be argued at your house. Time passes and a dispute begins to brew. Now, I want to argue at my house, not at yours. You pay costs to argue at my house that you wouldn’t have incurred had I done as agreed. Should I have to reimburse your costs?
No-Damage-for-Delay and Owner-Related Dispute Clauses are No Defense to Surety Liability Under Miller Act
Prime Government Contractors - you may need to update your interim payment waivers.
Contractual Fairness is Whatever the Parties’ Agreed
When you know a current action or inaction is wrong, but you do not object, should you be allowed to object later?
Which Comes First – Specifications or Drawings?
Sometimes it's not better to ask for forgiveness after-the-fact.
Government Contract Claims: When Appeal is Rejection of Settlement
Without a reservation of rights, appealing a Contracting Officer’s Final Decision is a rejection of any offer of payment or settlement included therein. So, the contractor had only three options.










