When you know a current action or inaction is wrong, but you do not object, should you be allowed to object later? Typical notions of fairness may suggest the answer is no. But, contractual fairness is whatever the parties’ agreed would be fair before the wrong action or inaction ever occurred.
In September 2009, a Contractor agreed to perform reconstruction work on a hurricane protection levee in St. Charles Parish, Louisiana. The Contract included specific requirements for the placement of geotextile fabric. With the U.S. Army Corps of Engineers inspectors onsite and observing, the Contractor installed (or placed) most of the total fabric for the Project. The Contractor also submitted QC reports detailing how the fabric was placed. The Corps acknowledged receipt of the Contractor’s QC reports and took no exceptions to the Contractor’s methodology.
Only after the Project was about 2/3 complete, did the Corps reject the Contractor’s placement methodology as being contrary to the Contract requirements. The Corps demanded all the fabric that was already placed and covered with fill be uncovered and re-placed. The Contractor understandably objected, but had to comply and filed a certified claim seeking recovery.
The Armed Services Board of Contract Appeals held the Contract requirements were not ambiguous (i.e., the Contractor should have known it was placing the fabric incorrectly).
The Contractor is in a tough spot. It thought that its interpretation of the Contract was reasonable and correct. So, the Contractor thought it was unnecessary to formally confirm its understanding with the Corps before beginning work. Additionally, the Contractor probably thought its understanding was confirmed when the Corps inspectors did not object.
This story is not over. The Contractor may yet prevail at a hearing. The text of the fabric placement requirements is included in the link below. Do you think it’s unclear?
Roads & Bridges
Where Does the Buck Stop?
Jon is a monthly contributor to Roads & Bridges magazine. He has been writing the law section for the magazine since January 2020. The link below will take you directly to the Roads & Bridges […]
Pay-If-Paid Unenforceable in Virginia Starting Jan. 1, 2023
As of Jan. 1, 2023, pay-if-paid clauses are unenforceable, regardless of whether a surety/payment bond claim is involved. This is only for subcontracts created on/after 1/1/23.
Also for subcontracts created on/after 1/1/23, the prime must specifically […]
How Short is Too Short
A limitations period is too short when it’s unreasonably short.
Construction Contracting Without Relief Clauses During COVID-19
What to do if your contract lacks the parts to handle COVID-19? Considerations for creating new contracts during COVID-19.
Your Contract Can Handle COVID-19
Uncertainty and risk are not new or novel to contractors. Contracts reduce uncertainty and share the risk of doing or providing something. COVID-19 may have contributed to, but it has not single-handedly created, uncertainty and risk.
Contractors Can Use RFI to Notify the Government
The Board (and the government) should not elevate form over substance in evaluating the sufficiency of a contractor’s notice.
Taxes Due!
It’s tax season again, so it’s time to pay the piper.
Contractor Wins when Government Reconsiders Accord
Ever had buyer’s remorse or second-guessed a decision? When the U.S. Army Corps of Engineers did that, a Contractor won its claim for time and money.
On a flood control project near Nogales, Arizona, severe flooding […]
Claim Certified with Digital Signature Deemed OK
The law is not a trend-setter. It doesn’t readily change or adapt to tech. So, a commonplace practice in business became a dispute when a claimant digitally certified a claim under the Contract Disputes Act.

Jonathan J. Straw
Blog Author
Contact Jonathan
Partner | KraftsonCaudle.com
Download Jon’s Bio
