The White House has directed Agency heads to “terminate or modify . . . covered contracts.” With some exceptions, there are numerous potential contracts on the chopping block. What should contractors do?
Upon receipt of a unilateral modification, assess whether the cost or time will increase in unchanged areas. For example, deductive changes for certain work could increase costs for other work that must still be performed. If costs were increased because of deductive changes, then carefully consider submitting a request for equitable adjustment.
Upon receipt of a notice of complete termination for convenience, promptly stop incurring further costs and, within one year of the termination, present a reasonable and well-supported termination settlement proposal to the Government under FAR 52.249-2(e). Recoverable costs include:
1. Costs actually incurred;
2. Profit on the work actually done; and
3. Costs of preparing a termination settlement proposal.
Upon receipt of a notice of partial termination for convenience, promptly stop incurring costs related to the terminated portion of the work and present a request for equitable adjustment within 90 days of the notice under FAR 52.249-2(l).
HEADER PHOTO: Termination by Nick Youngson CC BY-SA 3.0 Alpha Stock Images
Prime Contractor Had No Duty to Help Surety Investigate Sub’s Default
We all know what happens when we “ASS-U-ME” something. So, we should all carefully avoid assuming things unnecessarily.
It’s Good to Be the King
Mel Brooks in the movie History of the World: Part I (1981) said it best – “It’s good to be the King.” It’s also true when asserting claims against the State or an arm or agent of the State.
Smoke Without Fire: Damage from Concrete Dust Covered by Insurance
You’ve heard, “where there’s smoke, there’s fire.” In this instance, the smoke was concrete dust that damaged a warehouse full of aircraft […]
Changes Made After Substantial Completion Did Not Extend Overall Project Time
Contractors take heed – a time extension may be issued after substantial completion for specific work and the Government can still assess […]
One-Sided Construction Arbitration Clause Valid in Virginia
When it’s time to butt heads, know how the local turf (court) will interpret the clause.
Manage the Risk of Construction Changes
Almost any problem on a construction project can be traced to one of two things: changes or delays (even delays are really just changes). As in life, embrace and manage the change don’t run from it.
Want Your Profit? Prove a Constructive Change, Not a Suspension of Work.
What’s the Difference Between a Suspension of Work and a Constructive Change? For federal contractors, there are two main differences: . . .
No Special Defenses to Arbitration Agreements
Arbitration agreements, whether they are separate or part of a larger agreement, are contracts – an enforceable set of promises between parties. […]
How to Find (and Confirm) the Plain Meaning in a Contract
Contract formation confirms the parties understand and agree to all the essential terms. When that understanding and agreement fades, how do you […]