If all apples are fruit, then why are all fruit not apples? Because the part does not represent the whole. A Government Contractor discovered this when it learned that all unsuitable material was unsatisfactory material; but, all unsatisfactory material was not unsuitable material. Let me explain . . .
Under a Contract with the U.S. Army Corps of Engineers for two explosives storage magazines and a storm drain at Picatinny Arsenal, New Jersey, “unsatisfactory materials” were to be replaced with satisfactory materials. Basically, “unsatisfactory materials” included anything that could not be used as backfill.
As is typical, the Corps answered several pre-bid questions that later became amendments to the Contract. One of the Corps’ answers stated, “assume unsuitable material is not encountered.” The Contractor improperly equated “unsuitable material” with “unsatisfactory material.”
Although the term “unsuitable material” was not separately defined in the Contract, the Court found that other Contract provisions (e.g., pre-bid Q&A’s, specs, and soil borings) helped to define it as “unsatisfactory material” but only at certain depths/locations. Thus, the pre-bid Q&A did not pertain to “unsatisfactory materials” generally; but, only a subset of unsatisfactory materials – “unsuitable materials.”
While the whole included the part (unsatisfactory material included all unsuitable material), the part did not equal the whole (unsuitable material did not include all unsatisfactory material).
Roads & Bridges | Written Notice
WRITTEN NOTICE | Beware that strict compliance of the contract might be required.
When an owner replaced a contractor for significant safety violations, […]
Roads & Bridges | Mommie Dearest
MOMMY DEAREST | The story of an ESA without a MOM
Nobody enters this world, or a contract, without a mother: There can […]
IIJA | Does Closing a “Giant Loophole” Cost Contractors?
A recent article published by Roads and Bridges magazine reports that the Office of Management and Budget is working to broaden the scope […]
Roads & Bridges | Buy American Plan Gets an Update
BUY AMERICAN PLAN GETS AN UPDATE
The Office of Management and Budget is developing standards to replace the current Buy […]
Roads & Bridges
Where Does the Buck Stop?
WHERE DOES THE BUCK STOP? | A shallow concrete pour leads to an interesting lawsuit
On the desk of President Harry S. Truman […]
Roads & Bridges | Reshaping Agreements
RESHAPING AGREEMENTS | Oral Agreements Must Be Written in Stone
Reuse, reshaping, and/or reapplication of existing materials was the goal in this roadway […]
Pay-If-Paid Unenforceable in Virginia Starting Jan. 1, 2023
As of Jan. 1, 2023, pay-if-paid clauses are unenforceable, regardless of whether a surety/payment bond claim is involved. This is only for […]
How Short is Too Short
A limitations period is too short when it’s unreasonably short.
Construction Contracting Without Relief Clauses During COVID-19
What to do if your contract lacks the parts to handle COVID-19? Considerations for creating new contracts during COVID-19.

Jonathan J. Straw
Blog Author
Contact Jonathan
Partner | KraftsonCaudle.com
Download Jon’s Bio
