Since Y2K, sureties for federal projects in Virginia have been unable to defend against bond lawsuits by asserting pay-if-paid or pay-when paid clauses. Now, sureties are also unable to rely upon no-damage-for-delay (ND4D) and owner-related disputes clauses.
Recently, the Federal District Court for the Eastern District of Virginia held that a Prime’s Surety could not use the ND4D clause to defend against a Sub’s Miller Act lawsuit. Neither was the Sub required to wait until resolution of delays that the Owner may have caused, despite an express subcontract provision requiring as much.
The Court held that “the subcontract cannot eliminate the right to payment altogether, or delay it, unless the subcontract does so in a manner consistent with the terms of the Miller Act.” The only consistent means of which this author knows, and which the Court endorsed, were interim payment waivers for work already performed. The Court likened ND4D clauses to prospective waivers, which the Court said are prohibited by the Miller Act (although no such language exists in the Act).
Roads & Bridges | Written Notice
WRITTEN NOTICE | Beware that strict compliance of the contract might be required.
When an owner replaced a contractor for significant safety violations, […]
Roads & Bridges | Mommie Dearest
MOMMY DEAREST | The story of an ESA without a MOM
Nobody enters this world, or a contract, without a mother: There can […]
IIJA | Does Closing a “Giant Loophole” Cost Contractors?
A recent article published by Roads and Bridges magazine reports that the Office of Management and Budget is working to broaden the scope […]
Roads & Bridges | Buy American Plan Gets an Update
BUY AMERICAN PLAN GETS AN UPDATE
The Office of Management and Budget is developing standards to replace the current Buy […]
Roads & Bridges
Where Does the Buck Stop?
WHERE DOES THE BUCK STOP? | A shallow concrete pour leads to an interesting lawsuit
On the desk of President Harry S. Truman […]
Roads & Bridges | Reshaping Agreements
RESHAPING AGREEMENTS | Oral Agreements Must Be Written in Stone
Reuse, reshaping, and/or reapplication of existing materials was the goal in this roadway […]
Pay-If-Paid Unenforceable in Virginia Starting Jan. 1, 2023
As of Jan. 1, 2023, pay-if-paid clauses are unenforceable, regardless of whether a surety/payment bond claim is involved. This is only for […]
How Short is Too Short
A limitations period is too short when it’s unreasonably short.
Construction Contracting Without Relief Clauses During COVID-19
What to do if your contract lacks the parts to handle COVID-19? Considerations for creating new contracts during COVID-19.

Jonathan J. Straw
Blog Author
Contact Jonathan
Partner | KraftsonCaudle.com
Download Jon’s Bio
