On March 2, 2018, the Governor approved an act of the Virginia General Assembly to make unenforceable pre-work waivers of lien rights by general contractors. Thankfully, this new law now extends to general contractors the same protections provided back in 2015 to all lower-tier subcontractors and suppliers. However, some risk still exists for general contractors that does not exist for lower tiers – pre-work waivers of claims by general contractors are still enforceable.
In 2015, the Virginia General Assembly and Governor amended Va. Code § 11-4.1:1 to prohibit waivers by subcontractors and suppliers of claim and lien rights before performing the work. Subs and suppliers can still waive claim and lien rights after performing the work upon which the claim and/or lien is based. The 2015 amendment did not protect General Contractors. (More on the 2015 amendment.)
On March 2, 2018, the Governor approved an amendment to Va. Code § 43-1, which makes unenforceable pre-work waivers of liens by General Contractors. This amendment will become law on July 1, 2018 and apply to contracts dated thereafter.
This amendment applies only to pre-work lien waivers. It does not expressly apply to contract language that seeks to waive or diminish general contractors’ claim rights, such as a no-damage-for-delay clause in a private contract.
Roads & Bridges
Where Does the Buck Stop?
Jon is a monthly contributor to Roads & Bridges magazine. He has been writing the law section for the magazine since January 2020. The link below will take you directly to the Roads & Bridges […]
Pay-If-Paid Unenforceable in Virginia Starting Jan. 1, 2023
As of Jan. 1, 2023, pay-if-paid clauses are unenforceable, regardless of whether a surety/payment bond claim is involved. This is only for subcontracts created on/after 1/1/23.
Also for subcontracts created on/after 1/1/23, the prime must specifically […]
How Short is Too Short
A limitations period is too short when it’s unreasonably short.
Construction Contracting Without Relief Clauses During COVID-19
What to do if your contract lacks the parts to handle COVID-19? Considerations for creating new contracts during COVID-19.
Your Contract Can Handle COVID-19
Uncertainty and risk are not new or novel to contractors. Contracts reduce uncertainty and share the risk of doing or providing something. COVID-19 may have contributed to, but it has not single-handedly created, uncertainty and risk.
Contractors Can Use RFI to Notify the Government
The Board (and the government) should not elevate form over substance in evaluating the sufficiency of a contractor’s notice.
Taxes Due!
It’s tax season again, so it’s time to pay the piper.
Contractor Wins when Government Reconsiders Accord
Ever had buyer’s remorse or second-guessed a decision? When the U.S. Army Corps of Engineers did that, a Contractor won its claim for time and money.
On a flood control project near Nogales, Arizona, severe flooding […]
Claim Certified with Digital Signature Deemed OK
The law is not a trend-setter. It doesn’t readily change or adapt to tech. So, a commonplace practice in business became a dispute when a claimant digitally certified a claim under the Contract Disputes Act.

Jonathan J. Straw
Blog Author
Contact Jonathan
Partner | KraftsonCaudle.com
Download Jon’s Bio
