A limitations period is too short when it’s unreasonably short.
Recently, the U.S. Court of Appeals for the Fourth Circuit affirmed the Maryland District Court upholding a one-year contractual limitations period for arbitration. Along with a separate contractual waiver any trial in a traditional court setting, the plaintiff was SOL when he didn’t demand arbitration within one year.
The Court reaffirmed its prior holding from a separate 2007 case that, generally, “limitations periods may be shortened by agreement, so long as the limitations period is not unreasonably short.” Absent the agreement, the plaintiff had three years to file a lawsuit for breach of contract.
See also: When typical limitations don’t apply.
Read, re-read, review, and thoroughly understand your contracts. It’s often better to reasonably act and be rejected than not act or be too late.
Bracey v. Lancaster Foods LLC, No. 19-1292 (4th Cir. Dec. 16, 2020)
Navigating the Requirements for Claims against Virginia Public Entities
Contractors making claims against Virginia public entities must follow ALL applicable requirements. Such requirements may be found in several places, so check […]
Virginia General Contractors Not Protected from Pre-Work Claim Waivers
On March 2, 2018, the Governor approved an act of the Virginia General Assembly to make unenforceable pre-work waivers of lien rights […]
Adding Terms to a Government Contract without Saying So
Imagine an incredulous Contractor asking, “Show me in the Contract where it says I’m supposed to do X?” The Government Contracting Officer smugly answers, “even though the Contract doesn’t say so, you must do it anyway.” Is that even possible, when, how?
Differing Site Conditions: When the Part Does Not Equal the Whole
If all apples are fruit, then why are all fruit not apples?
Forum Selection Can Be a Home-Court Advantage
I promise that any disputes between us will be argued at your house. Time passes and a dispute begins to brew. Now, I want to argue at my house, not at yours. You pay costs to argue at my house that you wouldn’t have incurred had I done as agreed. Should I have to reimburse your costs?
No-Damage-for-Delay and Owner-Related Dispute Clauses are No Defense to Surety Liability Under Miller Act
Prime Government Contractors - you may need to update your interim payment waivers.
Contractual Fairness is Whatever the Parties’ Agreed
When you know a current action or inaction is wrong, but you do not object, should you be allowed to object later?
Which Comes First – Specifications or Drawings?
Sometimes it's not better to ask for forgiveness after-the-fact.
Government Contract Claims: When Appeal is Rejection of Settlement
Without a reservation of rights, appealing a Contracting Officer’s Final Decision is a rejection of any offer of payment or settlement included therein. So, the contractor had only three options.