A limitations period is too short when it’s unreasonably short.
Recently, the U.S. Court of Appeals for the Fourth Circuit affirmed the Maryland District Court upholding a one-year contractual limitations period for arbitration. Along with a separate contractual waiver any trial in a traditional court setting, the plaintiff was SOL when he didn’t demand arbitration within one year.
The Court reaffirmed its prior holding from a separate 2007 case that, generally, “limitations periods may be shortened by agreement, so long as the limitations period is not unreasonably short.” Absent the agreement, the plaintiff had three years to file a lawsuit for breach of contract.
See also: When typical limitations don’t apply.
Read, re-read, review, and thoroughly understand your contracts. It’s often better to reasonably act and be rejected than not act or be too late.
Bracey v. Lancaster Foods LLC, No. 19-1292 (4th Cir. Dec. 16, 2020)
Prime Contractor Had No Duty to Help Surety Investigate Sub’s Default
We all know what happens when we “ASS-U-ME” something. So, we should all carefully avoid assuming things unnecessarily.
It’s Good to Be the King
Mel Brooks in the movie History of the World: Part I (1981) said it best – “It’s good to be the King.” It’s also true when asserting claims against the State or an arm or agent of the State.
Smoke Without Fire: Damage from Concrete Dust Covered by Insurance
You’ve heard, “where there’s smoke, there’s fire.” In this instance, the smoke was concrete dust that damaged a warehouse full of aircraft […]
Changes Made After Substantial Completion Did Not Extend Overall Project Time
Contractors take heed – a time extension may be issued after substantial completion for specific work and the Government can still assess […]
One-Sided Construction Arbitration Clause Valid in Virginia
When it’s time to butt heads, know how the local turf (court) will interpret the clause.
Manage the Risk of Construction Changes
Almost any problem on a construction project can be traced to one of two things: changes or delays (even delays are really just changes). As in life, embrace and manage the change don’t run from it.
Want Your Profit? Prove a Constructive Change, Not a Suspension of Work.
What’s the Difference Between a Suspension of Work and a Constructive Change? For federal contractors, there are two main differences: . . .
No Special Defenses to Arbitration Agreements
Arbitration agreements, whether they are separate or part of a larger agreement, are contracts – an enforceable set of promises between parties. […]
How to Find (and Confirm) the Plain Meaning in a Contract
Contract formation confirms the parties understand and agree to all the essential terms. When that understanding and agreement fades, how do you […]