Another post discussed that your existing contract can probably handle the risks related to COVID-19. But, what to do if you contract lacks the support to handle COVID-19 and what to consider when creating new contracts during COVID-19?
What if the contract does not have a force majeure or other relief clause? First, consider the language of any applicable changes clause. Second, review any governmental emergency relief acts that could help. Third, the common law doctrine of frustration may be available, under which an obligation may excused or discharged when a fundamental assumption of the contract is not true or something later occurs rendering performance physically impossible or commercially impracticable. However, a radical price increase alone is likely insufficient.
When creating new contracts during COVID-19, do not rely solely upon force majeure clauses. Because unforeseeability is an element of most clauses, parties contracting during an event will find it very difficult to argue they could not contemplate the potential impact of the event. Consider including or adapting a price acceleration provision to prescribe or liquidate relief.
Keep a Pass-Thru Claim Burning, Don’t Extinguish Liability
Prime contractors, have you ever submitted a subcontractor’s claim to a public owner? Subcontractors, have you ever wanted to submit a claim against the government, but you had no contract with government?
When You Can’t Recover from a Third-Party (The Economic Loss Doctrine)
Suppose that you (the Contractor) had extra costs and want payment for those extra costs from the designer.
Barbecue and Construction Contracts
While barbecue recipes can be short and simple, contracts can be long and complicated. Fundamentally, though, recipes are very much like contracts: what’s required, how much of each part/ingredient, in what order should they be assembled/added, when, and for how long?
Show Your Work
A mentor of mine once said that process and procedures can be more important than substance and results. Like solving a math problem, how you solve it is often more important than the answer itself. The same is true in resolving construction contract disputes with public owners.
Substandard is Not Defective
The government need not follow the industry standard. It can do less or more.
Hide, Seek, & Seek
Have you ever played hide and seek? If you are the seeker, do you win the game when you find the hidden person? Yes, of course! Unless, you’re a government contractor.
Contractor Schooled School
Have you ever done exactly what you were supposed to do, but it didn’t work and you were blamed anyway? Nevertheless, if contractors follow the owner’s plans and it still doesn’t work, the contractor may be without fault – this is as it should be.
Walk It Off, Keep Going
During a recent soccer game, my seven-year-old son took the ball squarely in the face. But, he walked it off and continued playing. Contractors must do the same with changes.
Are We There Yet?
Next time you close a deal, get the essential terms on paper and signed by all parties before it’s Miller Time.