As a Government Contractor, when have you agreed to perform a certain way, but later realized that another way is better for everybody? When the Government agrees, expressly or impliedly, to the alternative performance, it waives a credit for the unperformed work.
In a recent example, under a design-build contract, a Government Contractor agreed to construct permanent bridges over irrigation canals in El Paso County, TX. (As an aside, the coldest night of my life was spent in Guadalupe National Park, just east of this project at negative 15 degrees in December.) The Contractor’s original plan included temporary bridges. After contract award, the Contractor successfully and timely performed its work without the temporary bridges. The Army Corps of Engineers knew of the Contractor’s plan and the changes to that plan, but without objection. Nevertheless, the Government sought a credit for unperformed, temporary bridges.
The Armed Services Board of Contract Appeals held that where the Government agrees to a planned method, but then does not object to a change in that method, the Government waives a credit, if any, for the savings from the change in method.
Read more about this example at ENR.com: Board Backs Contractor In Corps Cost Discovery Dispute
Appeal of American West Construction, LLC, ASBCA No. 61094 (December 19, 2017).
Roads & Bridges | Caught in the Middle
CAUGHT IN THE MIDDLE
New Mexico bridge case highlights the importance of written agreements for changes and delay compensation
In construction contracting, hope for […]
Roads & Bridges | Wait and It’s Waived
WAIT AND IT’S WAIVED
Roads & Bridges | Supreme Court Ruling on Arbitration Delay
Don’t wait to arbitrate! Progressing too far down the litigation […]
Roads & Bridges | Court Defines When Contractors Can Withdraw Due to Mistakes
BIDDING BLUNDER
Roads & Bridges | Court Defines When Contractors Can Withdraw Due to Mistakes
For over 125 years, the vast majority of jurisdictions […]
FEDERAL CONTRACT TERMINATION OR MODIFICATION
The White House has directed Agency heads to “terminate or modify . . . covered contracts.” With some exceptions, there are […]
Roads & Bridges | Maximizing Damage Recovery
MAXIMIZING DAMAGE RECOVERY
Tracking Costs, Avoiding Duplication in Liquidated and Actual Damage Claims
A County and Contractor contracted for construction of a road and […]
Roads & Bridges | Roadwork, Delays and Disputes
ROADWORK, DELAYS, AND DISPUTES
The Subcontract Case In Pecos County, Texas
“Road construction is ubiquitous in our society. . . .” C&C Road […]
Roads & Bridges | Understanding Sovereign Immunity
UNDERSTANDING SOVEREIGN IMMUNITY| Public Contracts and Lessons from Recent Texas Cases
Generally, governmental entities are immune from lawsuits. One exception is contractual. If […]
Roads & Bridges | Indiana Court Upholds Broad ND4D Clause
INDIANA COURT UPHOLDS BROAD ND4D CLAUSE | Ruling Precludes Subcontractor Claims for Delay and Acceleration Damages
This is the story of an Indiana […]
Roads & Bridges | Some Conditions Apply
SOME CONDITIONS APPLY | The scope of insurance policy coverage and what the terms dictate
At some time or another, many have tried […]