As a Government Contractor, when have you agreed to perform a certain way, but later realized that another way is better for everybody?  When the Government agrees, expressly or impliedly, to the alternative performance, it waives a credit for the unperformed work.

In a recent example, under a design-build contract, a Government Contractor agreed to construct permanent bridges over irrigation canals in El Paso County, TX. (As an aside, the coldest night of my life was spent in Guadalupe National Park, just east of this project at negative 15 degrees in December.)  The Contractor’s original plan included temporary bridges.  After contract award, the Contractor successfully and timely performed its work without the temporary bridges.   The Army Corps of Engineers knew of the Contractor’s plan and the changes to that plan, but without objection.  Nevertheless, the Government sought a credit for unperformed, temporary bridges.

The Armed Services Board of Contract Appeals held that where the Government agrees to a planned method, but then does not object to a change in that method, the Government waives a credit, if any, for the savings from the change in method.

Read more about this example at ENR.com: Board Backs Contractor In Corps Cost Discovery Dispute

Appeal of American West Construction, LLC, ASBCA No. 61094 (December 19, 2017).

Published On: January 8, 2018

Share This Story, Choose Your Platform!

  • An Unpredictable Case Teaches Hard Lessons | Contract Termination

Roads & Bridges | Contract Termination

September 9, 2024|

CONTRACT TERMINATION | An unpredictable case teaches hard lessons to each party involved

Court decisions are “opinions.” There are majority and dissenting (disagreeing) […]

Roads & Bridges | Liquidated Damages

February 24, 2024|

LIQUIDATED DAMAGES | Penalties and What is Unenforceable

Liquidated damages typically flow from delays, but they are not always solidly enforced.

In June 2017, […]

  • Roads & Bridges | Warranty Provisions

Roads& Bridges | Warranty Provisions

January 25, 2024|

WARRANTY PROVISIONS | Contracts must be interpreted thoroughly to avoid absurd results

You are responsible for things within your control. Be careful if […]

Roads& Bridges | Confusing Waters

October 17, 2023|

CONFUSING WATERS | A Supreme Court ruling leaves room for ambiguity

What happens when there may be a “significant nexus” between “adjacent” and/or […]

Share This Story, Choose Your Platform!

Jonathan J. Straw
Best Lawyers® - Jonathan Straw | 2026

Share This Story, Choose Your Platform!