Construction project professionals routinely send e-mails with “signatures,” which typically include the sender’s typewritten name, title, contact information, and/or company logo. But, this sort of e-mail “signature” is not enough to certify a claim to the Government.
A recent decision of the Armed Services Board of Contract Appeals dismissed an appeal by finding the claimant’s typical e-mail signature was not enough to properly certify a claim. The Board stated proper signatures could have been handwritten or digital (as applied in a pdf).
On a project for the U.S. Army Corps of Engineers at Manas International Airport, Kyrgyzstan, the Contractor submitted a claim by attaching it to an e-mail. The Contractor properly included all the words certifying the claim in the body of the transmittal e-mail. The “Director” for the Contractor “signed” the e-mail with his typewritten name, title, and contact information (a typical e-mail “signature” block).
Under FAR § 2.101, a proper signature is “a discrete, verifiable symbol of an individual.” Under this Board decision, there are two proper signatures:
- A handwritten signature or
- Digital signature (as in a pdf).
But, other types of proper signatures could include:
- Fingerprint or
- Photograph of your face (think about unlocking an iPhoneX).
These other types were not addressed by this Board decision, but could be considered “discrete, verifiable symbol(s) of an individual.” Nevertheless, I would stick with the tried and true handwritten signature.
Interestingly, the Board did not discuss how a password necessary to digitally sign a pdf compares to the password access necessary to send an e-mail. If the two are comparably secure, then a typewritten e-mail signature block should be as effective as digitally signing a pdf.
Navigating the Requirements for Claims against Virginia Public Entities
Contractors making claims against Virginia public entities must follow ALL applicable requirements. Such requirements may be found in several places, so check […]
Virginia General Contractors Not Protected from Pre-Work Claim Waivers
On March 2, 2018, the Governor approved an act of the Virginia General Assembly to make unenforceable pre-work waivers of lien rights […]
Adding Terms to a Government Contract without Saying So
Imagine an incredulous Contractor asking, “Show me in the Contract where it says I’m supposed to do X?” The Government Contracting Officer smugly answers, “even though the Contract doesn’t say so, you must do it anyway.” Is that even possible, when, how?
Differing Site Conditions: When the Part Does Not Equal the Whole
If all apples are fruit, then why are all fruit not apples?
Forum Selection Can Be a Home-Court Advantage
I promise that any disputes between us will be argued at your house. Time passes and a dispute begins to brew. Now, I want to argue at my house, not at yours. You pay costs to argue at my house that you wouldn’t have incurred had I done as agreed. Should I have to reimburse your costs?
No-Damage-for-Delay and Owner-Related Dispute Clauses are No Defense to Surety Liability Under Miller Act
Prime Government Contractors - you may need to update your interim payment waivers.
Contractual Fairness is Whatever the Parties’ Agreed
When you know a current action or inaction is wrong, but you do not object, should you be allowed to object later?
Which Comes First – Specifications or Drawings?
Sometimes it's not better to ask for forgiveness after-the-fact.
Government Contract Claims: When Appeal is Rejection of Settlement
Without a reservation of rights, appealing a Contracting Officer’s Final Decision is a rejection of any offer of payment or settlement included therein. So, the contractor had only three options.