Construction project professionals routinely send e-mails with “signatures,” which typically include the sender’s typewritten name, title, contact information, and/or company logo. But, this sort of e-mail “signature” is not enough to certify a claim to the Government.
A recent decision of the Armed Services Board of Contract Appeals dismissed an appeal by finding the claimant’s typical e-mail signature was not enough to properly certify a claim. The Board stated proper signatures could have been handwritten or digital (as applied in a pdf).
On a project for the U.S. Army Corps of Engineers at Manas International Airport, Kyrgyzstan, the Contractor submitted a claim by attaching it to an e-mail. The Contractor properly included all the words certifying the claim in the body of the transmittal e-mail. The “Director” for the Contractor “signed” the e-mail with his typewritten name, title, and contact information (a typical e-mail “signature” block).
Under FAR § 2.101, a proper signature is “a discrete, verifiable symbol of an individual.” Under this Board decision, there are two proper signatures:
- A handwritten signature or
- Digital signature (as in a pdf).
But, other types of proper signatures could include:
- Fingerprint or
- Photograph of your face (think about unlocking an iPhoneX).
These other types were not addressed by this Board decision, but could be considered “discrete, verifiable symbol(s) of an individual.” Nevertheless, I would stick with the tried and true handwritten signature.
Interestingly, the Board did not discuss how a password necessary to digitally sign a pdf compares to the password access necessary to send an e-mail. If the two are comparably secure, then a typewritten e-mail signature block should be as effective as digitally signing a pdf.
Prime Contractor Had No Duty to Help Surety Investigate Sub’s Default
We all know what happens when we “ASS-U-ME” something. So, we should all carefully avoid assuming things unnecessarily.
It’s Good to Be the King
Mel Brooks in the movie History of the World: Part I (1981) said it best – “It’s good to be the King.” It’s also true when asserting claims against the State or an arm or agent of the State.
Smoke Without Fire: Damage from Concrete Dust Covered by Insurance
You’ve heard, “where there’s smoke, there’s fire.” In this instance, the smoke was concrete dust that damaged a warehouse full of aircraft […]
Changes Made After Substantial Completion Did Not Extend Overall Project Time
Contractors take heed – a time extension may be issued after substantial completion for specific work and the Government can still assess […]
One-Sided Construction Arbitration Clause Valid in Virginia
When it’s time to butt heads, know how the local turf (court) will interpret the clause.
Manage the Risk of Construction Changes
Almost any problem on a construction project can be traced to one of two things: changes or delays (even delays are really just changes). As in life, embrace and manage the change don’t run from it.
Want Your Profit? Prove a Constructive Change, Not a Suspension of Work.
What’s the Difference Between a Suspension of Work and a Constructive Change? For federal contractors, there are two main differences: . . .
No Special Defenses to Arbitration Agreements
Arbitration agreements, whether they are separate or part of a larger agreement, are contracts – an enforceable set of promises between parties. […]
How to Find (and Confirm) the Plain Meaning in a Contract
Contract formation confirms the parties understand and agree to all the essential terms. When that understanding and agreement fades, how do you […]