Remember the adage, “what you say today could bite you tomorrow.”
Recently, a Contractor won its argument before the Armed Services Board of Contract Appeals (ASBCA) because the other party to the contract (the U.S. Army) prevented its own defense by insisting upon its own words and later trying to escape them.
Under a contract with the U.S. Army, Appellant/Contractor agreed to provide role-playing, human actors to help train soldiers to deal with civilians on a battlefield. Before the Army had issued the third of at least six task orders, the Contractor submitted a Request for Equitable Adjustment under Task Order No. 2.
In settling the Contractor’s Request for Equitable Adjustment, the Army drafted the language of a Contract Modification (Mod) stating “there are no further requests for equitable adjustments or claims to be submitted under this contract.” The Mod language was not limited to claims or requests by the Contractor. As such, the language included claims or requests by the Contractor AND the Army. This was the linchpin. Later, the Army lost its claim against the Contractor for damages related to Task Order No. 2 as the very language drafted by the Army in Mod 4 prevented the Army’s later claim.
Appeal of Supply & Service Team GmbH, ASBCA No. 59630, decided March 1, 2017.
Navigating the Requirements for Claims against Virginia Public Entities
Contractors making claims against Virginia public entities must follow ALL applicable requirements. Such requirements may be found in several places, so check […]
Virginia General Contractors Not Protected from Pre-Work Claim Waivers
On March 2, 2018, the Governor approved an act of the Virginia General Assembly to make unenforceable pre-work waivers of lien rights […]
Adding Terms to a Government Contract without Saying So
Imagine an incredulous Contractor asking, “Show me in the Contract where it says I’m supposed to do X?” The Government Contracting Officer smugly answers, “even though the Contract doesn’t say so, you must do it anyway.” Is that even possible, when, how?
Differing Site Conditions: When the Part Does Not Equal the Whole
If all apples are fruit, then why are all fruit not apples?
Forum Selection Can Be a Home-Court Advantage
I promise that any disputes between us will be argued at your house. Time passes and a dispute begins to brew. Now, I want to argue at my house, not at yours. You pay costs to argue at my house that you wouldn’t have incurred had I done as agreed. Should I have to reimburse your costs?
No-Damage-for-Delay and Owner-Related Dispute Clauses are No Defense to Surety Liability Under Miller Act
Prime Government Contractors - you may need to update your interim payment waivers.
Contractual Fairness is Whatever the Parties’ Agreed
When you know a current action or inaction is wrong, but you do not object, should you be allowed to object later?
Which Comes First – Specifications or Drawings?
Sometimes it's not better to ask for forgiveness after-the-fact.
Government Contract Claims: When Appeal is Rejection of Settlement
Without a reservation of rights, appealing a Contracting Officer’s Final Decision is a rejection of any offer of payment or settlement included therein. So, the contractor had only three options.