Remember the adage, “what you say today could bite you tomorrow.”
Recently, a Contractor won its argument before the Armed Services Board of Contract Appeals (ASBCA) because the other party to the contract (the U.S. Army) prevented its own defense by insisting upon its own words and later trying to escape them.
Under a contract with the U.S. Army, Appellant/Contractor agreed to provide role-playing, human actors to help train soldiers to deal with civilians on a battlefield. Before the Army had issued the third of at least six task orders, the Contractor submitted a Request for Equitable Adjustment under Task Order No. 2.
In settling the Contractor’s Request for Equitable Adjustment, the Army drafted the language of a Contract Modification (Mod) stating “there are no further requests for equitable adjustments or claims to be submitted under this contract.” The Mod language was not limited to claims or requests by the Contractor. As such, the language included claims or requests by the Contractor AND the Army. This was the linchpin. Later, the Army lost its claim against the Contractor for damages related to Task Order No. 2 as the very language drafted by the Army in Mod 4 prevented the Army’s later claim.
Appeal of Supply & Service Team GmbH, ASBCA No. 59630, decided March 1, 2017.
Prime Contractor Had No Duty to Help Surety Investigate Sub’s Default
We all know what happens when we “ASS-U-ME” something. So, we should all carefully avoid assuming things unnecessarily.
It’s Good to Be the King
Mel Brooks in the movie History of the World: Part I (1981) said it best – “It’s good to be the King.” It’s also true when asserting claims against the State or an arm or agent of the State.
Smoke Without Fire: Damage from Concrete Dust Covered by Insurance
You’ve heard, “where there’s smoke, there’s fire.” In this instance, the smoke was concrete dust that damaged a warehouse full of aircraft […]
Changes Made After Substantial Completion Did Not Extend Overall Project Time
Contractors take heed – a time extension may be issued after substantial completion for specific work and the Government can still assess […]
One-Sided Construction Arbitration Clause Valid in Virginia
When it’s time to butt heads, know how the local turf (court) will interpret the clause.
Manage the Risk of Construction Changes
Almost any problem on a construction project can be traced to one of two things: changes or delays (even delays are really just changes). As in life, embrace and manage the change don’t run from it.
Want Your Profit? Prove a Constructive Change, Not a Suspension of Work.
What’s the Difference Between a Suspension of Work and a Constructive Change? For federal contractors, there are two main differences: . . .
No Special Defenses to Arbitration Agreements
Arbitration agreements, whether they are separate or part of a larger agreement, are contracts – an enforceable set of promises between parties. […]
How to Find (and Confirm) the Plain Meaning in a Contract
Contract formation confirms the parties understand and agree to all the essential terms. When that understanding and agreement fades, how do you […]