Among its other duties, the Defense Logistics Agency is charged with disposing of and re-purposing certain surplus military equipment. After several years of failing to keep up with such duties, the Government outsourced the work to a Contractor. With the RFP, the Government’s work estimate included: (1) historical workload data and (2) workload projections.
Soon after performance began, the Contractor encountered a significant backlog of work. No information about a backlog was included in the RFP or related communication. The Government refused to negotiate an equitable adjustment, denied the Contractor’s claim, and the Court of Federal Claims found no fault by the Government.
The Federal Circuit Court of Appeals reversed the decision of the Court of Federal Claims and held the Government’s negligent estimate failed to provide the “most current information available.” Such information included the Government’s knowledge that there was a significant backlog of work facing the Contractor. The Government’s obligation to provide a “realistic estimate [including] the most current information available” doesn’t mean it must go out and create such information. Rather, to the extent such information exists, the Government must share it with the Contractor.
Although the Government’s behavior was only negligent (i.e., not intentional), it seems like a trick to withhold pertinent information while demanding the work be performed and refusing to pay for it.
Ultimately, the Contractor was entitled to an equitable adjustment to the contract price and time for the backlog.
Agility Defense & Government Services, Inc. v. United States, 847 F.3d 1345 (Fed. Cir. 2017)
Roads & Bridges
Where Does the Buck Stop?
Jon is a monthly contributor to Roads & Bridges magazine. He has been writing the law section for the magazine since January 2020. The link below will take you directly to the Roads & Bridges […]
Pay-If-Paid Unenforceable in Virginia Starting Jan. 1, 2023
As of Jan. 1, 2023, pay-if-paid clauses are unenforceable, regardless of whether a surety/payment bond claim is involved. This is only for subcontracts created on/after 1/1/23.
Also for subcontracts created on/after 1/1/23, the prime must specifically […]
How Short is Too Short
A limitations period is too short when it’s unreasonably short.
Construction Contracting Without Relief Clauses During COVID-19
What to do if your contract lacks the parts to handle COVID-19? Considerations for creating new contracts during COVID-19.
Your Contract Can Handle COVID-19
Uncertainty and risk are not new or novel to contractors. Contracts reduce uncertainty and share the risk of doing or providing something. COVID-19 may have contributed to, but it has not single-handedly created, uncertainty and risk.
Contractors Can Use RFI to Notify the Government
The Board (and the government) should not elevate form over substance in evaluating the sufficiency of a contractor’s notice.
Taxes Due!
It’s tax season again, so it’s time to pay the piper.
Contractor Wins when Government Reconsiders Accord
Ever had buyer’s remorse or second-guessed a decision? When the U.S. Army Corps of Engineers did that, a Contractor won its claim for time and money.
On a flood control project near Nogales, Arizona, severe flooding […]
Claim Certified with Digital Signature Deemed OK
The law is not a trend-setter. It doesn’t readily change or adapt to tech. So, a commonplace practice in business became a dispute when a claimant digitally certified a claim under the Contract Disputes Act.

Jonathan J. Straw
Blog Author
Contact Jonathan
Partner | KraftsonCaudle.com
Download Jon’s Bio
