Uncertainty and risk are not new or novel to contractors. Contracts reduce uncertainty and share the risk of doing or providing something. COVID-19 may have contributed to, but it has not single-handedly created, uncertainty and risk. Your contract toolbox may already be equipped to handle labor shortages, supply-chain disruptions, restrictive government action, and the like.
Many contracts already include some type of clause providing relief for unlikely delays to the project: Force Majeure, Acts of God, Acts of Government, or more generically, Delays and Extensions of Time. Under the AIA’s A-201 (2017), Section 8.3.1, the contractor is entitled to additional time for “unusual delay in deliveries” or “other causes beyond the Contractor’s control.” Under ConsensusDocs 200 (Rev. May 2017), Section 6.3.1, additional time may be afforded for delays “by any cause beyond the control of the Constructor . . . [including] epidemics.”
To preserve your rights and seek relief, contractors must effectively be doing three things: Notice, Mitigate, and Prove.
First, give timely and proper written notice under the contract terms. If notice must be written, send it to the proper person (e.g., Contracting Officer) using the proper means (e.g., regular mail may be required although e-mail is ubiquitous). Timely notice is probably required within a certain number of days of the event(s) giving rise to the claim condition. Repeated notice may be necessary for sub-events that, although they are related to the greatest event (i.e., COVID-19), they may be construed as unique events requiring unique notice. Do not assume that later-occurring events will automatically be covered by an earlier, blanket notice.
Second, reasonably mitigate the delays and damages arising from the event(s). Contractors will not be excused if they could have overcome difficulties posed by COVID-19 and completed work on time by reasonable alternatives. For example, if the supply chain is cut off or delayed, diligently try to find another supply chain and seek suitable substitutes that can be timely and economically acquired. Even if the contracting parties disagree over the cause, extent, or price of a change or delay, contractors must continue performance pending resolution of the change.
Third, prove the delays and damages were caused by the claimed event(s). The mere existence of a pandemic or quarantine, even one with world-wide effect, does not automatically excuse contractors from delay or default. Contractors must still prove the default was actually caused by the claimed event(s). Proof is a concurrent, not successor, activity to notice and mitigation. Start now, if you haven’t already, by maintaining adequate documentation. There is no later substitute for failing to document now. Sufficient documentation should include enough detail that disinterested decision-makers can objectively understand and agree with your situation and find your actions were reasonable in light of all the circumstances, without your additional oral explanation.
A future post will address: (1) issues facing contractors without such clauses and (2) suggestions for creating new contracts in the midst of COVID-19.
Navigating the Requirements for Claims against Virginia Public Entities
Contractors making claims against Virginia public entities must follow ALL applicable requirements. Such requirements may be found in several places, so check […]
Virginia General Contractors Not Protected from Pre-Work Claim Waivers
On March 2, 2018, the Governor approved an act of the Virginia General Assembly to make unenforceable pre-work waivers of lien rights […]
Adding Terms to a Government Contract without Saying So
Imagine an incredulous Contractor asking, “Show me in the Contract where it says I’m supposed to do X?” The Government Contracting Officer smugly answers, “even though the Contract doesn’t say so, you must do it anyway.” Is that even possible, when, how?
Differing Site Conditions: When the Part Does Not Equal the Whole
If all apples are fruit, then why are all fruit not apples?
Forum Selection Can Be a Home-Court Advantage
I promise that any disputes between us will be argued at your house. Time passes and a dispute begins to brew. Now, I want to argue at my house, not at yours. You pay costs to argue at my house that you wouldn’t have incurred had I done as agreed. Should I have to reimburse your costs?
No-Damage-for-Delay and Owner-Related Dispute Clauses are No Defense to Surety Liability Under Miller Act
Prime Government Contractors - you may need to update your interim payment waivers.
Contractual Fairness is Whatever the Parties’ Agreed
When you know a current action or inaction is wrong, but you do not object, should you be allowed to object later?
Which Comes First – Specifications or Drawings?
Sometimes it's not better to ask for forgiveness after-the-fact.
Government Contract Claims: When Appeal is Rejection of Settlement
Without a reservation of rights, appealing a Contracting Officer’s Final Decision is a rejection of any offer of payment or settlement included therein. So, the contractor had only three options.