Too often I’ve heard, “we didn’t want to rock the boat, so we just discussed the problem, but didn’t provide written notice.” But, remember The Godfather – “It’s not personal, it’s strictly business.”
Under a contract to furnish and install HVAC piping for a U.S. Army training facility at Joint Base Elmendorf-Richardson in Anchorage, Alaska, the Contractor argued the contract drawings and specs lacked the design details necessary to perform the work. The Contractor submitted several RFIs.
The Government argued the Contractor must use a letter, not an RFI, to notify the Contracting Officer of design problems. The Board held the information conveyed in the Contractor’s RFIs was sufficient to notify the government of a design discrepancy and “the Board (and the government) should not elevate form over substance in evaluating the sufficiency of a contractor’s notice.”
The Government also argued that the Contractor bore the risk of performing the changed work before the CO responded to the Contractor’s notice. Holding in the Contractor’s favor, the Board reasoned the risk borne by the Contractor is the risk of an incorrect course of action. If the Contractor takes the correct course of action (i.e., if it performs the work exactly as the CO would have directed) the Government suffers no harm, so the Contractor bears no such risk. When the Contractor acts before the CO responds, the Contractor bears the risk of taking incorrect action. If you’re gonna act, make it the correct action.
This case did not decide which party was at fault for the missing design details (i.e., Spearin Doctrine). But, [spoiler alert] the Government doesn’t automatically bear such responsibility even if it is a design-bid-build contract.
Appeal of UNIT Company, Armed Services Board of Contract Appeals, No. 60581 (Feb. 12, 2018).
Virginia General Contractors Not Protected from Pre-Work Claim Waivers
On March 2, 2018, the Governor approved an act of the Virginia General Assembly to make unenforceable pre-work waivers of lien rights […]
Adding Terms to a Government Contract without Saying So
Imagine an incredulous Contractor asking, “Show me in the Contract where it says I’m supposed to do X?” The Government Contracting Officer smugly answers, “even though the Contract doesn’t say so, you must do it anyway.” Is that even possible, when, how?
Differing Site Conditions: When the Part Does Not Equal the Whole
If all apples are fruit, then why are all fruit not apples?
Forum Selection Can Be a Home-Court Advantage
I promise that any disputes between us will be argued at your house. Time passes and a dispute begins to brew. Now, I want to argue at my house, not at yours. You pay costs to argue at my house that you wouldn’t have incurred had I done as agreed. Should I have to reimburse your costs?
No-Damage-for-Delay and Owner-Related Dispute Clauses are No Defense to Surety Liability Under Miller Act
Prime Government Contractors - you may need to update your interim payment waivers.
Contractual Fairness is Whatever the Parties’ Agreed
When you know a current action or inaction is wrong, but you do not object, should you be allowed to object later?
Which Comes First – Specifications or Drawings?
Sometimes it's not better to ask for forgiveness after-the-fact.
Government Contract Claims: When Appeal is Rejection of Settlement
Without a reservation of rights, appealing a Contracting Officer’s Final Decision is a rejection of any offer of payment or settlement included therein. So, the contractor had only three options.
Linking Obligations
If you want to bind the subcontractor to the prime in every way the same as the prime is bound to the owner, then the incorporation clause of the subcontract should be: . . .