Imagine you’re a Government Contractor under a firm, fixed-price contract and you’ve done nothing wrong. Nevertheless, the Government has decided to unilaterally end its contract with you. Yes, the Government can do this (for almost any reason). No, you cannot get your anticipated profit for unperformed work. You can only recover:
- Costs you actually incurred;
- Profit on the work actually done; and
- Costs of preparing a termination settlement proposal.
Costs actually incurred include preparing to perform (e.g., costs incurred after award and before notice-to-proceed) because “a settlement should compensate the contractor fairly for the work done and preparations made for the terminated portions of the contract…”). FAR 49.201(a); Appeal of Pro-Built Construction Firm, ASBCA No. 59278 (June 1, 2017).
“Cost and accounting data may provide guides, but are not rigid measures, for ascertaining fair compensation.” FAR 49.201(c). But, contract line items (CLINs) regarding price have no meaning in a T4C settlement focused on costs. Appeal of Atlas Sahil Construction Co., ASBCA No. 58951 (November 9, 2017).
If you get a T4C notice, promptly stop incurring further costs and present a reasonable and well-supported termination settlement proposal to the Government.
Termination for Convenience was OK to Get a Lower Price
When Massachusetts’ highest State court rejected Federal law on termination for convenience (T4C) a public entity’s “sole discretion . . . for […]
Pirates (Parties) Should Arbitrate Arbitrability
Yes, the word “pirates” is an anagram for “parties.” Participants in a lawsuit, arbitration, or mediation are collectively referred to as parties. Are they pirates too?
Very Bad Behavior Without Bad Faith is Not a Breach of Contract
Despite “abhorrent” behavior by the Army Corps of Engineers, a majority of the Armed Services Board of Contract Appeals held there was […]
Government Construction Contracts Require Bonds, Even When Contract Doesn’t Say So
Yesterday (Nov. 5, 2018), the Fed. Cir. Ct. of Appeals again endorsed the Christian doctrine, which can make unstated requirements part of a government contract.
Government’s Negligent Estimate a Trick?
The Government’s negligent estimate failed to provide the “most current information available.”
Prime Contractor Had No Duty to Help Surety Investigate Sub’s Default
We all know what happens when we “ASS-U-ME” something. So, we should all carefully avoid assuming things unnecessarily.
It’s Good to Be the King
Mel Brooks in the movie History of the World: Part I (1981) said it best – “It’s good to be the King.” It’s also true when asserting claims against the State or an arm or agent of the State.
Smoke Without Fire: Damage from Concrete Dust Covered by Insurance
You’ve heard, “where there’s smoke, there’s fire.” In this instance, the smoke was concrete dust that damaged a warehouse full of aircraft […]
Changes Made After Substantial Completion Did Not Extend Overall Project Time
Contractors take heed – a time extension may be issued after substantial completion for specific work and the Government can still assess […]










