Imagine you’re a Government Contractor under a firm, fixed-price contract and you’ve done nothing wrong. Nevertheless, the Government has decided to unilaterally end its contract with you. Yes, the Government can do this (for almost any reason). No, you cannot get your anticipated profit for unperformed work. You can only recover:
- Costs you actually incurred;
- Profit on the work actually done; and
- Costs of preparing a termination settlement proposal.
Costs actually incurred include preparing to perform (e.g., costs incurred after award and before notice-to-proceed) because “a settlement should compensate the contractor fairly for the work done and preparations made for the terminated portions of the contract…”). FAR 49.201(a); Appeal of Pro-Built Construction Firm, ASBCA No. 59278 (June 1, 2017).
“Cost and accounting data may provide guides, but are not rigid measures, for ascertaining fair compensation.” FAR 49.201(c). But, contract line items (CLINs) regarding price have no meaning in a T4C settlement focused on costs. Appeal of Atlas Sahil Construction Co., ASBCA No. 58951 (November 9, 2017).
If you get a T4C notice, promptly stop incurring further costs and present a reasonable and well-supported termination settlement proposal to the Government.
Prime Contractor Had No Duty to Help Surety Investigate Sub’s Default
We all know what happens when we “ASS-U-ME” something. So, we should all carefully avoid assuming things unnecessarily.
It’s Good to Be the King
Mel Brooks in the movie History of the World: Part I (1981) said it best – “It’s good to be the King.” It’s also true when asserting claims against the State or an arm or agent of the State.
Smoke Without Fire: Damage from Concrete Dust Covered by Insurance
You’ve heard, “where there’s smoke, there’s fire.” In this instance, the smoke was concrete dust that damaged a warehouse full of aircraft […]
Changes Made After Substantial Completion Did Not Extend Overall Project Time
Contractors take heed – a time extension may be issued after substantial completion for specific work and the Government can still assess […]
One-Sided Construction Arbitration Clause Valid in Virginia
When it’s time to butt heads, know how the local turf (court) will interpret the clause.
Manage the Risk of Construction Changes
Almost any problem on a construction project can be traced to one of two things: changes or delays (even delays are really just changes). As in life, embrace and manage the change don’t run from it.
Want Your Profit? Prove a Constructive Change, Not a Suspension of Work.
What’s the Difference Between a Suspension of Work and a Constructive Change? For federal contractors, there are two main differences: . . .
No Special Defenses to Arbitration Agreements
Arbitration agreements, whether they are separate or part of a larger agreement, are contracts – an enforceable set of promises between parties. […]
How to Find (and Confirm) the Plain Meaning in a Contract
Contract formation confirms the parties understand and agree to all the essential terms. When that understanding and agreement fades, how do you […]