Has your work on a government contract ever been delayed by another contractor? Did you (the prime contractor) have no control over the other contractor or entity? Did the Government promise you the other contractor would not inhibit your work? If yes to all three, consider the following success story of a Contractor’s recovery for delays against the Government caused by a third-party:
The successful Contractor under an IDIQ contract to perform canal excavation and sediment removal for the Department of Agriculture in St. Bernard Parish, Louisiana. Contractor encountered delays due to the continued presence of another contractor under a separate government contract at the same project site.
Key to the recovery was that during pre-bid site visit, the Contractor asked if the third-party’s work would be complete prior to the Contractor starting work. The Government replied, “Yes!” Fortunately for the Contractor, the pre-bid Q&A’s were made a part of the Contract by the Government’s own express direction.
Generally, the Government is not responsible for delays caused by third parties, even other contractors at its own project site, unless the Government affirmatively indicates the site will be ready and available.
The Civilian Board of Contract Appeals found the pre-bid Q&A’s were sufficient to establish a warranty by the Government that the site would be available. The Contractor recovered from the Government for the delays caused by the third-party contractor.
Insurance Company Had No Duty to Defend Under Eight Corners Rule
To decide if an insurer has a duty to defend, a Virginia State or Federal Court may only look at the allegations in the complaint and the insurance policy to determine if a judgment against the insured will be covered by the policy.
Owner SOL When Mandatory Mediation Didn’t Toll Statute of Limitations
Contract interpretation strives to find the meaning of all parts together.
Government Must Review Claims in Good Faith, Not “Conjure Up” a “Baseless Retaliation”
A contracting officer’s review of certified claims submitted in good faith is not intended to be a negotiating game where the agency may deny meritorious claims to gain leverage over the contractor.
Termination for Convenience was OK to Get a Lower Price
When Massachusetts’ highest State court rejected Federal law on termination for convenience (T4C) a public entity’s “sole discretion . . . for […]
Pirates (Parties) Should Arbitrate Arbitrability
Yes, the word “pirates” is an anagram for “parties.” Participants in a lawsuit, arbitration, or mediation are collectively referred to as parties. Are they pirates too?
Very Bad Behavior Without Bad Faith is Not a Breach of Contract
Despite “abhorrent” behavior by the Army Corps of Engineers, a majority of the Armed Services Board of Contract Appeals held there was […]
Government Construction Contracts Require Bonds, Even When Contract Doesn’t Say So
Yesterday (Nov. 5, 2018), the Fed. Cir. Ct. of Appeals again endorsed the Christian doctrine, which can make unstated requirements part of a government contract.
Government’s Negligent Estimate a Trick?
The Government’s negligent estimate failed to provide the “most current information available.”
Prime Contractor Had No Duty to Help Surety Investigate Sub’s Default
We all know what happens when we “ASS-U-ME” something. So, we should all carefully avoid assuming things unnecessarily.