Suppose that you (the Contractor) had extra costs and want payment for those extra costs from the designer.  But,

  • No property was damaged,
  • Nobody got hurt (thankfully), and
  • There is no contract between you and the designer.

Likely Result: You cannot recover from the designer because of the economic loss doctrine, which usually applies when the facts listed above are true.

Possible Solutions:

  1. Carefully negotiate your scope of risk under the contract;
  2. Trust but verify (consider using an independent design reviewer pre- or post-bid and pre-construction);
  3. Manage, coordinate, and communicate; and/or
  4. Apply an exception to the rule (depending on which State you’re in and the unique facts of the scenario).

 

Here’s a recent example from the highest court of Maryland where the contractor (unfortunately) lost:

Under a contract with the City of Baltimore, the Contractor agreed to construct improvements to a wastewater treatment plant including construction of giant concrete tubs to hold untreated wastewater.  The Contractor constructed the tubs per the third-party engineer’s design, but the tubs leaked.  The Contractor sued the engineer for money damages, no persons were injured and no property was damaged from the leaking tubs.

The highest court in the State of Maryland denied the Contractor’s recovery from the engineer.  The court denied the contractor’s request for two main reasons.  First, the City, Contractor, and engineer had carefully limited their risk by the complex construction contracts, so there was no need for the court after-the-fact to adjust the limits of that risk.  Second, adjusting the limits of the agreed-upon risk could result in higher costs for future public construction projects and, since public projects are often funded with taxpayers’ dollars, then taxpayers would be funding the potentially higher costs.  [Editorial note: I generally agree with the court’s first reason, but find the second reason flimsy.]

Balfour Beatty Infrastructure, Inc. v. Rummel Klepper & Kahl, LLP, 451 Md. 600 (2017)

Published On: July 6, 2017

Share This Story, Choose Your Platform!

Barbecue and Construction Contracts

June 28, 2017|

While barbecue recipes can be short and simple, contracts can be long and complicated.  Fundamentally, though, recipes are very much like contracts: what’s required, how much of each part/ingredient, in what order should they be assembled/added, when, and for how long?

Show Your Work

June 19, 2017|

A mentor of mine once said that process and procedures can be more important than substance and results.  Like solving a math problem, how you solve it is often more important than the answer itself.  The same is true in resolving construction contract disputes with public owners.

Hide, Seek, & Seek

May 30, 2017|

Have you ever played hide and seek? If you are the seeker, do you win the game when you find the hidden person? Yes, of course! Unless, you’re a government contractor.

Contractor Schooled School

May 22, 2017|

Have you ever done exactly what you were supposed to do, but it didn’t work and you were blamed anyway? Nevertheless, if contractors follow the owner’s plans and it still doesn’t work, the contractor may be without fault – this is as it should be.

Walk It Off, Keep Going

May 15, 2017|

During a recent soccer game, my seven-year-old son took the ball squarely in the face. But, he walked it off and continued playing. Contractors must do the same with changes.

Are We There Yet?

May 8, 2017|

Next time you close a deal, get the essential terms on paper and signed by all parties before it’s Miller Time.

Share This Story, Choose Your Platform!

Jonathan J. Straw
Best Lawyers® - Jonathan Straw | 2026

Share This Story, Choose Your Platform!