During a recent soccer game, my seven-year-old son took the ball squarely in the face.  But, he walked it off and continued playing.  Contractors must do the same with changes.

In 2006, under a contract with NAVFAC for repairs to a wastewater treatment system at Naval Station Guantanamo Bay Cuba, the Contractor encountered differing site conditions.  NAVFAC did not issue a suspension or stop work order, but the Contractor stopped working awaiting responses to RFIs.  NAVFAC did not respond to all the RFIs.  So, the Contractor submitted a certified claim, but the Contractor never resumed work.  The Contractor should have continued working.

Under the Federal Acquisition Regulations, the Contractor is obligated to “prosecute the work diligently” and continue performance pending the outcome of a claim. (FAR 52.211-10 and 52.233-1(i)).  Doing so not only mitigates potential delays and damages, but it ensures that when a claim is submitted, a “sum certain” (i.e., showing of damage) is possible.

In this case, the Contractor’s claim submission was premature and the Contractor’s refusal to perform directed or constructive changes pending the promise of payment precluded the ASBCA from having any power to resolve the dispute.  The ASBCA dismissed the Contractor’s appeal because the Contractor sought future damages for work it had not yet performed.  At worst, NAVFAC could have terminated the Contractor for default.

Appeal of Islands Mechanical Contractor, Inc., ASBCA No. 59655 (April 13, 2017)

Published On: May 15, 2017

Share This Story, Choose Your Platform!

Forum Selection Can Be a Home-Court Advantage

March 1, 2018|

I promise that any disputes between us will be argued at your house.  Time passes and a dispute begins to brew.  Now, I want to argue at my house, not at yours.  You pay costs to argue at my house that you wouldn’t have incurred had I done as agreed.  Should I have to reimburse your costs?

Linking Obligations

January 24, 2018|

If you want to bind the subcontractor to the prime in every way the same as the prime is bound to the owner, then the incorporation clause of the subcontract should be: . . .

Termination of Government Contracts for Convenience (T4C)

January 16, 2018|

Imagine you’re a Government Contractor under a firm, fixed-price contract and you’ve done nothing wrong.  Nevertheless, the Government has decided to unilaterally end its contract with you.  Yes, the Government can do this...

Government Contractors: Build a Snowman in August

January 8, 2018|

As a Government Contractor, when have you agreed to perform a certain way, but later realized that another way is better for everybody?  When the Government agrees, expressly or impliedly, to the alternative performance, it waives a credit for the unperformed work.

Share This Story, Choose Your Platform!

Jonathan J. Straw
Best Lawyers® - Jonathan Straw | 2026

Share This Story, Choose Your Platform!