During a recent soccer game, my seven-year-old son took the ball squarely in the face.  But, he walked it off and continued playing.  Contractors must do the same with changes.

In 2006, under a contract with NAVFAC for repairs to a wastewater treatment system at Naval Station Guantanamo Bay Cuba, the Contractor encountered differing site conditions.  NAVFAC did not issue a suspension or stop work order, but the Contractor stopped working awaiting responses to RFIs.  NAVFAC did not respond to all the RFIs.  So, the Contractor submitted a certified claim, but the Contractor never resumed work.  The Contractor should have continued working.

Under the Federal Acquisition Regulations, the Contractor is obligated to “prosecute the work diligently” and continue performance pending the outcome of a claim. (FAR 52.211-10 and 52.233-1(i)).  Doing so not only mitigates potential delays and damages, but it ensures that when a claim is submitted, a “sum certain” (i.e., showing of damage) is possible.

In this case, the Contractor’s claim submission was premature and the Contractor’s refusal to perform directed or constructive changes pending the promise of payment precluded the ASBCA from having any power to resolve the dispute.  The ASBCA dismissed the Contractor’s appeal because the Contractor sought future damages for work it had not yet performed.  At worst, NAVFAC could have terminated the Contractor for default.

Appeal of Islands Mechanical Contractor, Inc., ASBCA No. 59655 (April 13, 2017)

Published On: May 15, 2017

Share This Story, Choose Your Platform!

E-mail Signature Not Enough to Certify a Claim

December 5, 2017|

Construction project professionals routinely send e-mails with “signatures,” which typically include the sender’s typewritten name, title, contact information, and/or company logo.  But, this sort of e-mail “signature” is not enough to certify a claim to the Government.

Constructive Acceleration

November 14, 2017|

Contractors know that time is money.  So, the point is clear when expressly told to “Speed Up!  Go Faster!”

But, what do you […]

Construction Contracts & Whodunit

November 7, 2017|

Imagine reading a crime novel and just when you think you figured out whodunit, a plot twist suggests a different culprit. In construction contracting, finding the right answer can be a difficult task when

Owner Nonpayment is No Defense to Miller Act Claim

October 24, 2017|

As if you needed confirmation that the Federal Miller Act is a powerful tool for unpaid subcontractors, this is it.  Even when a Prime ordered and accepted the Sub’s work, but didn’t have to pay under the Subcontract, the Subcontractor still. . . .

Trust, but Verify

October 17, 2017|

Rely at your own risk upon a Contracting Officer’s statements when statutes or contract provisions may conflict.

Share This Story, Choose Your Platform!

Jonathan J. Straw
Best Lawyers® - Jonathan Straw | 2026

Share This Story, Choose Your Platform!