During a recent soccer game, my seven-year-old son took the ball squarely in the face. But, he walked it off and continued playing. Contractors must do the same with changes.
In 2006, under a contract with NAVFAC for repairs to a wastewater treatment system at Naval Station Guantanamo Bay Cuba, the Contractor encountered differing site conditions. NAVFAC did not issue a suspension or stop work order, but the Contractor stopped working awaiting responses to RFIs. NAVFAC did not respond to all the RFIs. So, the Contractor submitted a certified claim, but the Contractor never resumed work. The Contractor should have continued working.
Under the Federal Acquisition Regulations, the Contractor is obligated to “prosecute the work diligently” and continue performance pending the outcome of a claim. (FAR 52.211-10 and 52.233-1(i)). Doing so not only mitigates potential delays and damages, but it ensures that when a claim is submitted, a “sum certain” (i.e., showing of damage) is possible.
In this case, the Contractor’s claim submission was premature and the Contractor’s refusal to perform directed or constructive changes pending the promise of payment precluded the ASBCA from having any power to resolve the dispute. The ASBCA dismissed the Contractor’s appeal because the Contractor sought future damages for work it had not yet performed. At worst, NAVFAC could have terminated the Contractor for default.
Appeal of Islands Mechanical Contractor, Inc., ASBCA No. 59655 (April 13, 2017)
Termination for Convenience was OK to Get a Lower Price
When Massachusetts’ highest State court rejected Federal law on termination for convenience (T4C) a public entity’s “sole discretion . . . for […]
Pirates (Parties) Should Arbitrate Arbitrability
Yes, the word “pirates” is an anagram for “parties.” Participants in a lawsuit, arbitration, or mediation are collectively referred to as parties. Are they pirates too?
Very Bad Behavior Without Bad Faith is Not a Breach of Contract
Despite “abhorrent” behavior by the Army Corps of Engineers, a majority of the Armed Services Board of Contract Appeals held there was […]
Government Construction Contracts Require Bonds, Even When Contract Doesn’t Say So
Yesterday (Nov. 5, 2018), the Fed. Cir. Ct. of Appeals again endorsed the Christian doctrine, which can make unstated requirements part of a government contract.
Government’s Negligent Estimate a Trick?
The Government’s negligent estimate failed to provide the “most current information available.”
Prime Contractor Had No Duty to Help Surety Investigate Sub’s Default
We all know what happens when we “ASS-U-ME” something. So, we should all carefully avoid assuming things unnecessarily.
It’s Good to Be the King
Mel Brooks in the movie History of the World: Part I (1981) said it best – “It’s good to be the King.” It’s also true when asserting claims against the State or an arm or agent of the State.
Smoke Without Fire: Damage from Concrete Dust Covered by Insurance
You’ve heard, “where there’s smoke, there’s fire.” In this instance, the smoke was concrete dust that damaged a warehouse full of aircraft […]
Changes Made After Substantial Completion Did Not Extend Overall Project Time
Contractors take heed – a time extension may be issued after substantial completion for specific work and the Government can still assess […]










