Do you remember the Choose Your Own Adventure books? If you are a subcontractor on a federal project, where should you bring a lawsuit to get paid? If you are a prime contractor on a federal project, would you like the convenience of defending such a lawsuit in your own backyard?
The Federal Miller Act is designed to enforce payment for work on public buildings and public works when the U.S. Government is a party to the prime contract. Typically, a lawsuit by a subcontractor or material supplier seeking payment must be filed in the same geographic area where the Project is located. (40 USC § 3133(b)(3)(B)). However, a forum selection clause may differ and determine where such a lawsuit must be filed.
In mid-July 2015, a Federal District Court transferred a case from Connecticut to Virginia by applying a valid forum selection clause in a Miller Act lawsuit. The project was for refurbishment of a barracks building located at the U.S. Coast Guard Academy in New London, Connecticut. Typically then, Connecticut would be the proper place to file a Miller Act lawsuit.
However, the subcontract provided that all “claims related in any way or manner to the Subcontract Work . . . shall be litigated in” Virginia. The Federal Court in Connecticut followed the same logic as some other Federal Circuits (1st, 5th, 8th, and 10th) and found that when the forum selection clause is otherwise valid, it will be upheld even when the Federal Statute does not expressly provide for anything different (i.e., the Federal Statute states the Miller Act lawsuit “must” be filed where the Project is located).
The Connecticut Federal District Court also noted that Virginia law, not Connecticut law, applied to interpret the Subcontract, but this alone was not a reason to transfer the case to Virginia.
Keystone: If your Project is located in any of the Federal Circuits following the same reasoning (1st, 5th, 8th, and 10th Circuits) and your subcontract provides for a specific place to file the lawsuit, you should consider it as a defensive maneuver as a prime contractor or for efficiency sake as a subcontractor.
Case: QSR Steel Corporation, LLC v. Safeco Insurance Co. of America, Case No. 3:14-1017 (U.S.D.C., Dist. Conn., July 16, 2015).
How to Find (and Confirm) the Plain Meaning in a Contract
Contract formation confirms the parties understand and agree to all the essential terms. When that understanding and agreement fades, how do you […]
Navigating the Requirements for Claims against Virginia Public Entities
Contractors making claims against Virginia public entities must follow ALL applicable requirements. Such requirements may be found in several places, so check […]
Virginia General Contractors Not Protected from Pre-Work Claim Waivers
On March 2, 2018, the Governor approved an act of the Virginia General Assembly to make unenforceable pre-work waivers of lien rights […]
Adding Terms to a Government Contract without Saying So
Imagine an incredulous Contractor asking, “Show me in the Contract where it says I’m supposed to do X?” The Government Contracting Officer smugly answers, “even though the Contract doesn’t say so, you must do it anyway.” Is that even possible, when, how?
Differing Site Conditions: When the Part Does Not Equal the Whole
If all apples are fruit, then why are all fruit not apples?
Forum Selection Can Be a Home-Court Advantage
I promise that any disputes between us will be argued at your house. Time passes and a dispute begins to brew. Now, I want to argue at my house, not at yours. You pay costs to argue at my house that you wouldn’t have incurred had I done as agreed. Should I have to reimburse your costs?
No-Damage-for-Delay and Owner-Related Dispute Clauses are No Defense to Surety Liability Under Miller Act
Prime Government Contractors - you may need to update your interim payment waivers.
Contractual Fairness is Whatever the Parties’ Agreed
When you know a current action or inaction is wrong, but you do not object, should you be allowed to object later?
Which Comes First – Specifications or Drawings?
Sometimes it's not better to ask for forgiveness after-the-fact.