Not bad power, but the ability of a decision-maker (e.g., court) to decide which side is right (or which is more correct). A judge’s power is not automatic. Every court must first decide if it has the power to decide the parties’ dispute – whether it has jurisdiction over the subject matter and the parties involved. Without such power, no further decisions can be made.
Based upon recent guidance from the U.S. Supreme Court (Wilkins v. U.S., No. 21-1164, March 28, 2023), the U.S. Court of Appeals for the Federal Circuit held that the requirement to state a sum certain under the Contract Disputes Act of 1978 is NOT a jurisdictional requirement. Failure to state a sum certain does NOT deprive the decision-maker of power. Arguments regarding sum certain are subject to “disagreement on the merits” not dismissal for lack of jurisdiction because the claimant “organiz[ed] its sub-claims in a manner different from how the [Armed Services Board of Contract Appeals] would sub-divide claims” or how the Government would have preferred the claimant have sub-divided its claims. Although “a deficient sum certain may in some circumstances be a reason to reject all or part of a claim, it does not mean the Board lacks jurisdiction entirely.” The Federal Circuit did not describe or exemplify “some circumstances,” so stay tuned for what that means.
Claimants should still state a sum (or sums) certain or specific in their claims, no estimates or place-holders (see another post on this point). But now, if claimants are not specific, it can be cured without depriving the decision-maker of power to resolve the disputes.
Acceptance and Intervening Cause Avoided Construction Warranty Claim
Like cars, computers, and appliances, construction projects include warranties too. Similarly, construction project warranties are limited to causes within the contractor’s control […]
Insurance Company Had No Duty to Defend Under Eight Corners Rule
To decide if an insurer has a duty to defend, a Virginia State or Federal Court may only look at the allegations in the complaint and the insurance policy to determine if a judgment against the insured will be covered by the policy.
Owner SOL When Mandatory Mediation Didn’t Toll Statute of Limitations
Contract interpretation strives to find the meaning of all parts together.
Government Must Review Claims in Good Faith, Not “Conjure Up” a “Baseless Retaliation”
A contracting officer’s review of certified claims submitted in good faith is not intended to be a negotiating game where the agency may deny meritorious claims to gain leverage over the contractor.
Termination for Convenience was OK to Get a Lower Price
When Massachusetts’ highest State court rejected Federal law on termination for convenience (T4C) a public entity’s “sole discretion . . . for […]
Pirates (Parties) Should Arbitrate Arbitrability
Yes, the word “pirates” is an anagram for “parties.” Participants in a lawsuit, arbitration, or mediation are collectively referred to as parties. Are they pirates too?
Very Bad Behavior Without Bad Faith is Not a Breach of Contract
Despite “abhorrent” behavior by the Army Corps of Engineers, a majority of the Armed Services Board of Contract Appeals held there was […]
Government Construction Contracts Require Bonds, Even When Contract Doesn’t Say So
Yesterday (Nov. 5, 2018), the Fed. Cir. Ct. of Appeals again endorsed the Christian doctrine, which can make unstated requirements part of a government contract.
Government’s Negligent Estimate a Trick?
The Government’s negligent estimate failed to provide the “most current information available.”