Another post discussed that your existing contract can probably handle the risks related to COVID-19. But, what to do if you contract lacks the support to handle COVID-19 and what to consider when creating new contracts during COVID-19?
What if the contract does not have a force majeure or other relief clause? First, consider the language of any applicable changes clause. Second, review any governmental emergency relief acts that could help. Third, the common law doctrine of frustration may be available, under which an obligation may excused or discharged when a fundamental assumption of the contract is not true or something later occurs rendering performance physically impossible or commercially impracticable. However, a radical price increase alone is likely insufficient.
When creating new contracts during COVID-19, do not rely solely upon force majeure clauses. Because unforeseeability is an element of most clauses, parties contracting during an event will find it very difficult to argue they could not contemplate the potential impact of the event. Consider including or adapting a price acceleration provision to prescribe or liquidate relief.
Smoke Without Fire: Damage from Concrete Dust Covered by Insurance
You’ve heard, “where there’s smoke, there’s fire.” In this instance, the smoke was concrete dust that damaged a warehouse full of aircraft […]
Changes Made After Substantial Completion Did Not Extend Overall Project Time
Contractors take heed – a time extension may be issued after substantial completion for specific work and the Government can still assess […]
One-Sided Construction Arbitration Clause Valid in Virginia
When it’s time to butt heads, know how the local turf (court) will interpret the clause.
Manage the Risk of Construction Changes
Almost any problem on a construction project can be traced to one of two things: changes or delays (even delays are really just changes). As in life, embrace and manage the change don’t run from it.
Want Your Profit? Prove a Constructive Change, Not a Suspension of Work.
What’s the Difference Between a Suspension of Work and a Constructive Change? For federal contractors, there are two main differences: . . .
No Special Defenses to Arbitration Agreements
Arbitration agreements, whether they are separate or part of a larger agreement, are contracts – an enforceable set of promises between parties. […]
How to Find (and Confirm) the Plain Meaning in a Contract
Contract formation confirms the parties understand and agree to all the essential terms. When that understanding and agreement fades, how do you […]
Navigating the Requirements for Claims against Virginia Public Entities
Contractors making claims against Virginia public entities must follow ALL applicable requirements. Such requirements may be found in several places, so check […]
Virginia General Contractors Not Protected from Pre-Work Claim Waivers
On March 2, 2018, the Governor approved an act of the Virginia General Assembly to make unenforceable pre-work waivers of lien rights […]










