It’s tax season again, so it’s time to pay the piper. Despite your efforts to responsibly report and file your taxes with all the allowable deductions and/or adjustments, the Government will find a way to feed itself. The State of Connecticut found a way to do just that to a Contractor despite the State owing the Contractor on a judgment.
Following a successful arbitration, the State of Connecticut Department of Transportation owed to the Contractor a judgment of several million dollars. But, when the Contractor received payment of that judgment from the State, it was “short” by over one million dollars. Upon investigation, the Contractor learned that the State Comptroller had unilaterally reduced the judgment to cover the Contractor’s unpaid taxes. Such taxes were unrelated to the issues successfully arbitrated in the Contractor’s favor.
The Contractor valiantly argued the State could not reduce the judgment amount because the DOT failed to prove the taxes as a setoff or counterclaim during the arbitration. Indeed, the DOT alleged but did not put forth any evidence to prove the amount or that the taxes were overdue. Nevertheless, payment of the judgment triggered review by the Comptroller and State tax statutes authorized the withholding to pay the Contractor’s tax debt.
Paraphrasing an excerpt from Common Sense (1776) by Thomas Paine, government is like an octopus with too many arms and, when one arm fails, another rises to feed the beast.
Connecticut Department of Transportation v. White Oak Corporation, 332 Conn. 776 (Aug. 20, 2019).
Changes Made After Substantial Completion Did Not Extend Overall Project Time
Contractors take heed – a time extension may be issued after substantial completion for specific work and the Government can still assess […]
One-Sided Construction Arbitration Clause Valid in Virginia
When it’s time to butt heads, know how the local turf (court) will interpret the clause.
Manage the Risk of Construction Changes
Almost any problem on a construction project can be traced to one of two things: changes or delays (even delays are really just changes). As in life, embrace and manage the change don’t run from it.
Want Your Profit? Prove a Constructive Change, Not a Suspension of Work.
What’s the Difference Between a Suspension of Work and a Constructive Change? For federal contractors, there are two main differences: . . .
No Special Defenses to Arbitration Agreements
Arbitration agreements, whether they are separate or part of a larger agreement, are contracts – an enforceable set of promises between parties. […]
How to Find (and Confirm) the Plain Meaning in a Contract
Contract formation confirms the parties understand and agree to all the essential terms. When that understanding and agreement fades, how do you […]
Navigating the Requirements for Claims against Virginia Public Entities
Contractors making claims against Virginia public entities must follow ALL applicable requirements. Such requirements may be found in several places, so check […]
Virginia General Contractors Not Protected from Pre-Work Claim Waivers
On March 2, 2018, the Governor approved an act of the Virginia General Assembly to make unenforceable pre-work waivers of lien rights […]
Adding Terms to a Government Contract without Saying So
Imagine an incredulous Contractor asking, “Show me in the Contract where it says I’m supposed to do X?” The Government Contracting Officer smugly answers, “even though the Contract doesn’t say so, you must do it anyway.” Is that even possible, when, how?










