Despite “abhorrent” behavior by the Army Corps of Engineers, a majority of the Armed Services Board of Contract Appeals held there was no breach of the duty of good faith and fair dealing. Yet, the Contractor recovered almost all of its claimed damages because the Corps forced the Contractor to sign a modification under duress and ignored a significant constructive change.
In this story, two bids were submitted for maintenance dredging of the Scarborough River, Scarborough, Maine. The successful bidder was 40% lower than the Government’s initial estimate. Before contract award the Corps requested a change to the winning bidder’s plan at no additional cost to the Government and the Corps revised its Government estimate to be only 14% higher than the winning bid.
After award, the Corps unilaterally reduced the amounts it had agreed to pay for certain CLINs, which effectively cut off the contractor’s cash flow for the Project.
From these facts, a minority of the Board found the Corps breached its duty of good faith and fair dealing. However, a majority of the Board held there was no breach, despite the Corps’ “abhorrent” and unreasonable behavior. (A split of opinion on the Board is rare.)
The full opinion has more detail of how unfairly the Corps treated the Contractor.
Appeals of North American Landscaping, Construction, and Dredge, Co., Inc., Armed Services Board of Contract Appeals Nos. 60235, 60236, 60237, and 60238 (August 9, 2018).
Termination for Convenience was OK to Get a Lower Price
When Massachusetts’ highest State court rejected Federal law on termination for convenience (T4C) a public entity’s “sole discretion . . . for […]
Pirates (Parties) Should Arbitrate Arbitrability
Yes, the word “pirates” is an anagram for “parties.” Participants in a lawsuit, arbitration, or mediation are collectively referred to as parties. Are they pirates too?
Very Bad Behavior Without Bad Faith is Not a Breach of Contract
Despite “abhorrent” behavior by the Army Corps of Engineers, a majority of the Armed Services Board of Contract Appeals held there was […]
Government Construction Contracts Require Bonds, Even When Contract Doesn’t Say So
Yesterday (Nov. 5, 2018), the Fed. Cir. Ct. of Appeals again endorsed the Christian doctrine, which can make unstated requirements part of a government contract.
Government’s Negligent Estimate a Trick?
The Government’s negligent estimate failed to provide the “most current information available.”
Prime Contractor Had No Duty to Help Surety Investigate Sub’s Default
We all know what happens when we “ASS-U-ME” something. So, we should all carefully avoid assuming things unnecessarily.
It’s Good to Be the King
Mel Brooks in the movie History of the World: Part I (1981) said it best – “It’s good to be the King.” It’s also true when asserting claims against the State or an arm or agent of the State.
Smoke Without Fire: Damage from Concrete Dust Covered by Insurance
You’ve heard, “where there’s smoke, there’s fire.” In this instance, the smoke was concrete dust that damaged a warehouse full of aircraft […]
Changes Made After Substantial Completion Did Not Extend Overall Project Time
Contractors take heed – a time extension may be issued after substantial completion for specific work and the Government can still assess […]