Requirements may exist outside the four corners of the contract when such requirements are: (1) otherwise mandatory and (2) express a significant or deeply ingrained strand of public procurement policy. In other words, your contract may include requirements not shown or otherwise indicated in the contract documents.
In an example of this, a Contractor agreed to provide pre-engineered metal buildings for the Army’s use at Camp Edwards, Massachusetts. Under the Miller Act and the FAR, bonds for construction projects are mandatory. The mandate for payment bonds is based upon the “deeply ingrained strand of public procurement policy” that security should be provided for entities or persons furnishing labor and materials in the performance of government contracts. The mandate for performance bonds is due to the Government’s need for security to ensure the use of public funds results in a finished product since not completing a public project could be a waste or misuse of public funds. Of course, (dripping with sarcasm) we’ve never seen a public entity waste or misuse public funds, right.
The Armed Services Board of Contract Appeals held bonds were part of the contract even though bonding requirements were not expressly stated nor incorporated by reference. The U.S. Court of Appeals for the Federal Circuit agreed with the Board. K-Con, Inc. v. Secretary of the Army, U.S. Court of Appeals for the Federal Circuit, Case No.: 2017-2254 (Nov. 5, 2018).
Next time you review an RFP, carefully consider what you don’t see but that may still be required.
Read another short example here: Adding Terms to a Government Contract without Saying So.
Prime Contractor Had No Duty to Help Surety Investigate Sub’s Default
We all know what happens when we “ASS-U-ME” something. So, we should all carefully avoid assuming things unnecessarily.
It’s Good to Be the King
Mel Brooks in the movie History of the World: Part I (1981) said it best – “It’s good to be the King.” It’s also true when asserting claims against the State or an arm or agent of the State.
Smoke Without Fire: Damage from Concrete Dust Covered by Insurance
You’ve heard, “where there’s smoke, there’s fire.” In this instance, the smoke was concrete dust that damaged a warehouse full of aircraft […]
Changes Made After Substantial Completion Did Not Extend Overall Project Time
Contractors take heed – a time extension may be issued after substantial completion for specific work and the Government can still assess […]
One-Sided Construction Arbitration Clause Valid in Virginia
When it’s time to butt heads, know how the local turf (court) will interpret the clause.
Manage the Risk of Construction Changes
Almost any problem on a construction project can be traced to one of two things: changes or delays (even delays are really just changes). As in life, embrace and manage the change don’t run from it.
Want Your Profit? Prove a Constructive Change, Not a Suspension of Work.
What’s the Difference Between a Suspension of Work and a Constructive Change? For federal contractors, there are two main differences: . . .
No Special Defenses to Arbitration Agreements
Arbitration agreements, whether they are separate or part of a larger agreement, are contracts – an enforceable set of promises between parties. […]
How to Find (and Confirm) the Plain Meaning in a Contract
Contract formation confirms the parties understand and agree to all the essential terms. When that understanding and agreement fades, how do you […]