Mel Brooks in the movie History of the World: Part I (1981) said it best – “It’s good to be the King.” (See short movie clip.)
It’s also true when asserting claims against the State or an arm/agent of the State.
Whereas the State or a County may enter into contracts, their liability is limited solely to the terms of that contract. Similarly, liability of a contracting State is limited to breach of the contract and typically excludes claims or remedies outside the scope of the contract.
In a recent example, the Contractor agreed to make alterations and additions to a Public School’s facility. After delays and extra costs arose, the Contractor alleged two counts of breach of contract and one count each of unjust enrichment and quantum meruit. The Court dismissed the two latter counts by reviewing and applying the history and basis for the County’s sovereign immunity as an arm of the Commonwealth.
Contractors should style claims within the contract provisions. There is virtually no remedy against the State outside the contract. (See related post.)
Akian, Inc. and Penn. Nat’l. Mutual Casualty Ins. Co. v. Spotsylvania County Public Schools, 2018 Va. Cir. Lexis 329, CL18-2439 (Spotsylvania County Cir. Ct., Sep., 21, 2018).
Termination for Convenience was OK to Get a Lower Price
When Massachusetts’ highest State court rejected Federal law on termination for convenience (T4C) a public entity’s “sole discretion . . . for […]
Pirates (Parties) Should Arbitrate Arbitrability
Yes, the word “pirates” is an anagram for “parties.” Participants in a lawsuit, arbitration, or mediation are collectively referred to as parties. Are they pirates too?
Very Bad Behavior Without Bad Faith is Not a Breach of Contract
Despite “abhorrent” behavior by the Army Corps of Engineers, a majority of the Armed Services Board of Contract Appeals held there was […]
Government Construction Contracts Require Bonds, Even When Contract Doesn’t Say So
Yesterday (Nov. 5, 2018), the Fed. Cir. Ct. of Appeals again endorsed the Christian doctrine, which can make unstated requirements part of a government contract.
Government’s Negligent Estimate a Trick?
The Government’s negligent estimate failed to provide the “most current information available.”
Prime Contractor Had No Duty to Help Surety Investigate Sub’s Default
We all know what happens when we “ASS-U-ME” something. So, we should all carefully avoid assuming things unnecessarily.
It’s Good to Be the King
Mel Brooks in the movie History of the World: Part I (1981) said it best – “It’s good to be the King.” It’s also true when asserting claims against the State or an arm or agent of the State.
Smoke Without Fire: Damage from Concrete Dust Covered by Insurance
You’ve heard, “where there’s smoke, there’s fire.” In this instance, the smoke was concrete dust that damaged a warehouse full of aircraft […]
Changes Made After Substantial Completion Did Not Extend Overall Project Time
Contractors take heed – a time extension may be issued after substantial completion for specific work and the Government can still assess […]