Virginia Federal Court upholds unilateral arbitration clause in construction contract. On a Project for the United States Air Force at Langley Air Force Base in Hampton, Virginia, an electrical Subcontractor filed a lawsuit for nonpayment under the Federal Miller Act. The clause provided that at Prime’s “sole election, any and all disputes . . . may be decided by mediation, arbitration or [ADR] proceedings as chosen by [Prime].”
The Court upheld the clause finding: (1) it was not vague simply because only one party (the Prime) could invoke its terms when the other party (Subcontractor) had already agreed to allow the Prime this right and (2) the contract as a whole was supported by sufficient consideration (i.e., benefit or detriment to each party).
This appears to be the first case by a Virginia court (state or federal) to interpret and uphold such a clause, which allowed only the Prime Contractor, not the Subcontractor, to resolve disputes by arbitration. North Carolina, West Virginia, and now Virginia agree on upholding unilateral arbitration clauses. Maryland disagrees.
When it’s time to butt heads, know how the local turf (court) will interpret the clause.

U.S. f/u/b/o Harbor Construction Co., Inc. v. T.H.R. Enterprises, Inc., 311 F.Supp.3d 797 (U.S. District Ct., Eastern District of Virginia, April 26, 2018)
Prime Contractor Had No Duty to Help Surety Investigate Sub’s Default
We all know what happens when we “ASS-U-ME” something. So, we should all carefully avoid assuming things unnecessarily.
It’s Good to Be the King
Mel Brooks in the movie History of the World: Part I (1981) said it best – “It’s good to be the King.” It’s also true when asserting claims against the State or an arm or agent of the State.
Smoke Without Fire: Damage from Concrete Dust Covered by Insurance
You’ve heard, “where there’s smoke, there’s fire.” In this instance, the smoke was concrete dust that damaged a warehouse full of aircraft […]
Changes Made After Substantial Completion Did Not Extend Overall Project Time
Contractors take heed – a time extension may be issued after substantial completion for specific work and the Government can still assess […]
One-Sided Construction Arbitration Clause Valid in Virginia
When it’s time to butt heads, know how the local turf (court) will interpret the clause.
Manage the Risk of Construction Changes
Almost any problem on a construction project can be traced to one of two things: changes or delays (even delays are really just changes). As in life, embrace and manage the change don’t run from it.
Want Your Profit? Prove a Constructive Change, Not a Suspension of Work.
What’s the Difference Between a Suspension of Work and a Constructive Change? For federal contractors, there are two main differences: . . .
No Special Defenses to Arbitration Agreements
Arbitration agreements, whether they are separate or part of a larger agreement, are contracts – an enforceable set of promises between parties. […]
How to Find (and Confirm) the Plain Meaning in a Contract
Contract formation confirms the parties understand and agree to all the essential terms. When that understanding and agreement fades, how do you […]