What’s the difference between a suspension of work and a constructive change? For federal contractors, there are two important differences:

  1. If you want profit, prove a constructive change.
  2. If any other contract clause affords an equitable adjustment (e.g., Changes Clause), the Suspension of Work clause won’t help you.

To recover from a suspension of work, a contractor must show:

  1. Contract performance was delayed;
  2. Government directly caused the delay;
  3. The delay was for an unreasonable period of time; and
  4. The contractor suffered damages therefrom (excluding profit); and
  5. No other clause provides an equitable adjustment to the Contractor

FAR § 52.242-14

To prove a constructive change, a contractor must show:

  1. Any written or oral order from the Contracting Officer;
  2. Not a directed change;
  3. That caused a change;
  4. Contractor gave timely notice that it considered the order as a change; and
  5. The contractor suffered damages therefrom.

FAR § 52.243-4(b)

In a recent Civilian Board of Contract Appeals decision, the Board agreed with the contractor in finding an unreasonable delay (179 days) and awarded damages for a suspension of the work.  In the same decision, the Board also found a constructive change in the contractor’s favor.  The Board did not discuss why the suspension of work clause prevailed when the contractor may have been able to show a constructive change (unless, perhaps, notice of a constructive change was inadequate).

BCPeabody Construction Services, Inc. v. Dept. of Veterans Affairs, CBCA No. 5410, March 26, 2018

Published On: April 25, 2018

Share This Story, Choose Your Platform!

It’s Good to Be the King

October 16, 2018|

Mel Brooks in the movie History of the World: Part I (1981) said it best – “It’s good to be the King.”  It’s also true when asserting claims against the State or an arm or agent of the State.

Manage the Risk of Construction Changes

August 15, 2018|

Almost any problem on a construction project can be traced to one of two things: changes or delays (even delays are really just changes).  As in life, embrace and manage the change don’t run from it.

Share This Story, Choose Your Platform!

Jonathan J. Straw
Best Lawyers® - Jonathan Straw | 2026

Share This Story, Choose Your Platform!