If all apples are fruit, then why are all fruit not apples?  Because the part does not represent the whole.  A Government Contractor discovered this when it learned that all unsuitable material was unsatisfactory material; but, all unsatisfactory material was not unsuitable material.  Let me explain . . .

Under a Contract with the U.S. Army Corps of Engineers for two explosives storage magazines and a storm drain at Picatinny Arsenal, New Jersey, “unsatisfactory materials” were to be replaced with satisfactory materials.  Basically, “unsatisfactory materials” included anything that could not be used as backfill.

As is typical, the Corps answered several pre-bid questions that later became amendments to the Contract.  One of the Corps’ answers stated, “assume unsuitable material is not encountered.”  The Contractor improperly equated “unsuitable material” with “unsatisfactory material.”

Although the term “unsuitable material” was not separately defined in the Contract, the Court found that other Contract provisions (e.g., pre-bid Q&A’s, specs, and soil borings) helped to define it as “unsatisfactory material” but only at certain depths/locations.  Thus, the pre-bid Q&A did not pertain to “unsatisfactory materials” generally; but, only a subset of unsatisfactory materials – “unsuitable materials.”

While the whole included the part (unsatisfactory material included all unsuitable material), the part did not equal the whole (unsuitable material did not include all unsatisfactory material).

Senate Builders and Construction Managers, Inc. v. U.S., Ct. of Fed. Claims, Case No. 14-1196C (April 29, 2017).

Published On: March 8, 2018

Share This Story, Choose Your Platform!

Manage the Risk of Construction Changes

August 15, 2018|

Almost any problem on a construction project can be traced to one of two things: changes or delays (even delays are really just changes).  As in life, embrace and manage the change don’t run from it.

Adding Terms to a Government Contract without Saying So

March 14, 2018|

Imagine an incredulous Contractor asking, “Show me in the Contract where it says I’m supposed to do X?”  The Government Contracting Officer smugly answers, “even though the Contract doesn’t say so, you must do it anyway.”  Is that even possible, when, how?

Share This Story, Choose Your Platform!

Jonathan J. Straw
Best Lawyers® - Jonathan Straw | 2026

Share This Story, Choose Your Platform!