When you know a current action or inaction is wrong, but you do not object, should you be allowed to object later? Typical notions of fairness may suggest the answer is no. But, contractual fairness is whatever the parties’ agreed would be fair before the wrong action or inaction ever occurred.
In September 2009, a Contractor agreed to perform reconstruction work on a hurricane protection levee in St. Charles Parish, Louisiana. The Contract included specific requirements for the placement of geotextile fabric. With the U.S. Army Corps of Engineers inspectors onsite and observing, the Contractor installed (or placed) most of the total fabric for the Project. The Contractor also submitted QC reports detailing how the fabric was placed. The Corps acknowledged receipt of the Contractor’s QC reports and took no exceptions to the Contractor’s methodology.
Only after the Project was about 2/3 complete, did the Corps reject the Contractor’s placement methodology as being contrary to the Contract requirements. The Corps demanded all the fabric that was already placed and covered with fill be uncovered and re-placed. The Contractor understandably objected, but had to comply and filed a certified claim seeking recovery.
The Armed Services Board of Contract Appeals held the Contract requirements were not ambiguous (i.e., the Contractor should have known it was placing the fabric incorrectly).
The Contractor is in a tough spot. It thought that its interpretation of the Contract was reasonable and correct. So, the Contractor thought it was unnecessary to formally confirm its understanding with the Corps before beginning work. Additionally, the Contractor probably thought its understanding was confirmed when the Corps inspectors did not object.
This story is not over. The Contractor may yet prevail at a hearing. The text of the fabric placement requirements is included in the link below. Do you think it’s unclear?

Government’s Negligent Estimate a Trick?
The Government’s negligent estimate failed to provide the “most current information available.”
Prime Contractor Had No Duty to Help Surety Investigate Sub’s Default
We all know what happens when we “ASS-U-ME” something. So, we should all carefully avoid assuming things unnecessarily.
It’s Good to Be the King
Mel Brooks in the movie History of the World: Part I (1981) said it best – “It’s good to be the King.” It’s also true when asserting claims against the State or an arm or agent of the State.
Smoke Without Fire: Damage from Concrete Dust Covered by Insurance
You’ve heard, “where there’s smoke, there’s fire.” In this instance, the smoke was concrete dust that damaged a warehouse full of aircraft […]
Changes Made After Substantial Completion Did Not Extend Overall Project Time
Contractors take heed – a time extension may be issued after substantial completion for specific work and the Government can still assess […]
One-Sided Construction Arbitration Clause Valid in Virginia
When it’s time to butt heads, know how the local turf (court) will interpret the clause.
Manage the Risk of Construction Changes
Almost any problem on a construction project can be traced to one of two things: changes or delays (even delays are really just changes). As in life, embrace and manage the change don’t run from it.
Want Your Profit? Prove a Constructive Change, Not a Suspension of Work.
What’s the Difference Between a Suspension of Work and a Constructive Change? For federal contractors, there are two main differences: . . .
No Special Defenses to Arbitration Agreements
Arbitration agreements, whether they are separate or part of a larger agreement, are contracts – an enforceable set of promises between parties. […]