After much disagreement, the Owner, Designer, Insurer(s), and Contractor(s) have agreed to resolve their differences through a settlement. Do these things to help avoid future angst:
Written: All settlements should be written. A settlement is a new contract among the parties, so treat it as such. Besides, memories are fading faster than ever as we use more electronic media.
Essential Terms: Warranty, Indemnity, Confidentiality (detail all duties that end vs. those that continue).
Essential Documents: Don’t just reference other essential documents; attach them to the written settlement agreement (e.g., final lien/claim release, final change order, and/or tax forms).
Payment: Timing and Method. (If there will be damages for delay of settlement payment, consider adding a liquidated damages clause. Will payment be by wire transfer, physical check, credit, other?)
Enforcement: Include a liquidated damages provision if damages will come from delayed payment. And, since it’s a new contract, will you have to file another lawsuit to enforce the agreement? If so, consider a consent judgment where all parties pre-agree that if the terms are not met, a Court can efficiently and expeditiously enforce.
Closeout: Detail how, who, and when other issues will be closed (e.g., dismissal of all litigation or completion of outstanding work).
Navigating the Requirements for Claims against Virginia Public Entities
Contractors making claims against Virginia public entities must follow ALL applicable requirements. Such requirements may be found in several places, so check […]
Virginia General Contractors Not Protected from Pre-Work Claim Waivers
On March 2, 2018, the Governor approved an act of the Virginia General Assembly to make unenforceable pre-work waivers of lien rights […]
Adding Terms to a Government Contract without Saying So
Imagine an incredulous Contractor asking, “Show me in the Contract where it says I’m supposed to do X?” The Government Contracting Officer smugly answers, “even though the Contract doesn’t say so, you must do it anyway.” Is that even possible, when, how?
Differing Site Conditions: When the Part Does Not Equal the Whole
If all apples are fruit, then why are all fruit not apples?
Forum Selection Can Be a Home-Court Advantage
I promise that any disputes between us will be argued at your house. Time passes and a dispute begins to brew. Now, I want to argue at my house, not at yours. You pay costs to argue at my house that you wouldn’t have incurred had I done as agreed. Should I have to reimburse your costs?
No-Damage-for-Delay and Owner-Related Dispute Clauses are No Defense to Surety Liability Under Miller Act
Prime Government Contractors - you may need to update your interim payment waivers.
Contractual Fairness is Whatever the Parties’ Agreed
When you know a current action or inaction is wrong, but you do not object, should you be allowed to object later?
Which Comes First – Specifications or Drawings?
Sometimes it's not better to ask for forgiveness after-the-fact.
Government Contract Claims: When Appeal is Rejection of Settlement
Without a reservation of rights, appealing a Contracting Officer’s Final Decision is a rejection of any offer of payment or settlement included therein. So, the contractor had only three options.