Contractors know that time is money. So, the point is clear when expressly told to “Speed Up! Go Faster!”
But, what do you do when the Owner says, “You must still meet the deadline and I’m not giving you any more time.” Preserve and pursue a claim against the Owner for constructive acceleration.
Constructive acceleration occurs when the owner or government demands compliance with an original contract deadline, despite a delay. In such cases, the contractor may be entitled to reimbursement for expenses actually and reasonably incurred in complying with an (implied) acceleration order.
But, the Contractor must prove:
- Excusable Delay: a delay that is neither the fault of the owner or contractor;
- Request: The Contractor timely and sufficiently requested more time;
- Denial: Owner denied or failed to timely respond to Contractor’s request for more time;
- Demand: Owner demanded Contractor meet deadline;
- Timely Notice: Contractor timely notified Owner that Contractor understood the Owner’s demand as constructive acceleration; and
- Damages: Contractor incurred damages due to Owner’s unreasonable demand(s).
Prime Contractor Had No Duty to Help Surety Investigate Sub’s Default
We all know what happens when we “ASS-U-ME” something. So, we should all carefully avoid assuming things unnecessarily.
It’s Good to Be the King
Mel Brooks in the movie History of the World: Part I (1981) said it best – “It’s good to be the King.” It’s also true when asserting claims against the State or an arm or agent of the State.
Smoke Without Fire: Damage from Concrete Dust Covered by Insurance
You’ve heard, “where there’s smoke, there’s fire.” In this instance, the smoke was concrete dust that damaged a warehouse full of aircraft […]
Changes Made After Substantial Completion Did Not Extend Overall Project Time
Contractors take heed – a time extension may be issued after substantial completion for specific work and the Government can still assess […]
One-Sided Construction Arbitration Clause Valid in Virginia
When it’s time to butt heads, know how the local turf (court) will interpret the clause.
Manage the Risk of Construction Changes
Almost any problem on a construction project can be traced to one of two things: changes or delays (even delays are really just changes). As in life, embrace and manage the change don’t run from it.
Want Your Profit? Prove a Constructive Change, Not a Suspension of Work.
What’s the Difference Between a Suspension of Work and a Constructive Change? For federal contractors, there are two main differences: . . .
No Special Defenses to Arbitration Agreements
Arbitration agreements, whether they are separate or part of a larger agreement, are contracts – an enforceable set of promises between parties. […]
How to Find (and Confirm) the Plain Meaning in a Contract
Contract formation confirms the parties understand and agree to all the essential terms. When that understanding and agreement fades, how do you […]