Contractors know that time is money. So, the point is clear when expressly told to “Speed Up! Go Faster!”
But, what do you do when the Owner says, “You must still meet the deadline and I’m not giving you any more time.” Preserve and pursue a claim against the Owner for constructive acceleration.
Constructive acceleration occurs when the owner or government demands compliance with an original contract deadline, despite a delay. In such cases, the contractor may be entitled to reimbursement for expenses actually and reasonably incurred in complying with an (implied) acceleration order.
But, the Contractor must prove:
- Excusable Delay: a delay that is neither the fault of the owner or contractor;
- Request: The Contractor timely and sufficiently requested more time;
- Denial: Owner denied or failed to timely respond to Contractor’s request for more time;
- Demand: Owner demanded Contractor meet deadline;
- Timely Notice: Contractor timely notified Owner that Contractor understood the Owner’s demand as constructive acceleration; and
- Damages: Contractor incurred damages due to Owner’s unreasonable demand(s).
Government Must Review Claims in Good Faith, Not “Conjure Up” a “Baseless Retaliation”
A contracting officer’s review of certified claims submitted in good faith is not intended to be a negotiating game where the agency may deny meritorious claims to gain leverage over the contractor.
Termination for Convenience was OK to Get a Lower Price
When Massachusetts’ highest State court rejected Federal law on termination for convenience (T4C) a public entity’s “sole discretion . . . for […]
Pirates (Parties) Should Arbitrate Arbitrability
Yes, the word “pirates” is an anagram for “parties.” Participants in a lawsuit, arbitration, or mediation are collectively referred to as parties. Are they pirates too?
Very Bad Behavior Without Bad Faith is Not a Breach of Contract
Despite “abhorrent” behavior by the Army Corps of Engineers, a majority of the Armed Services Board of Contract Appeals held there was […]
Government Construction Contracts Require Bonds, Even When Contract Doesn’t Say So
Yesterday (Nov. 5, 2018), the Fed. Cir. Ct. of Appeals again endorsed the Christian doctrine, which can make unstated requirements part of a government contract.
Government’s Negligent Estimate a Trick?
The Government’s negligent estimate failed to provide the “most current information available.”
Prime Contractor Had No Duty to Help Surety Investigate Sub’s Default
We all know what happens when we “ASS-U-ME” something. So, we should all carefully avoid assuming things unnecessarily.
It’s Good to Be the King
Mel Brooks in the movie History of the World: Part I (1981) said it best – “It’s good to be the King.” It’s also true when asserting claims against the State or an arm or agent of the State.
Smoke Without Fire: Damage from Concrete Dust Covered by Insurance
You’ve heard, “where there’s smoke, there’s fire.” In this instance, the smoke was concrete dust that damaged a warehouse full of aircraft […]










