Here’s the situation – You’ve done the extra work because you were verbally asked and you strive to do a good job. But now, the Owner or Prime won’t pay because your Contract or Subcontract precludes payment without a written change order.
Even if your agreement can only be modified by a writing, you may still have a good argument to be paid for extra work.
Consider your prior dealings with the Owner or Prime on the current project and on prior projects. Have you ever been paid for extra work without a written change order? If yes, then you could still get paid even though the contract requires a written change order or other written agreement. The more frequently this happens between you and the other party, the better your chances of payment.
The Virginia Supreme Court has held a subcontract clause requiring a written agreement for changes did not pertain to work outside the scope of the original subcontract. Instead, the Subcontractor’s invoices were sufficient written documentation to show subsequent, separate agreements for the extra work. The Subcontractor’s daily reports supported that the Subcontractor actually performed the extra work. Also important is that the subcontract did not include a provision that excluded all other negotiations from the Subcontract (i.e., a merger or integration clause).
Medlin & Son Construction Co. v. The Matthews Group, Inc., No. 160050 (Va. Nov. 23, 2016)
It’s Good to Be the King
Mel Brooks in the movie History of the World: Part I (1981) said it best – “It’s good to be the King.” It’s also true when asserting claims against the State or an arm or agent of the State.
Smoke Without Fire: Damage from Concrete Dust Covered by Insurance
You’ve heard, “where there’s smoke, there’s fire.” In this instance, the smoke was concrete dust that damaged a warehouse full of aircraft […]
Changes Made After Substantial Completion Did Not Extend Overall Project Time
Contractors take heed – a time extension may be issued after substantial completion for specific work and the Government can still assess […]
One-Sided Construction Arbitration Clause Valid in Virginia
When it’s time to butt heads, know how the local turf (court) will interpret the clause.
Manage the Risk of Construction Changes
Almost any problem on a construction project can be traced to one of two things: changes or delays (even delays are really just changes). As in life, embrace and manage the change don’t run from it.
Want Your Profit? Prove a Constructive Change, Not a Suspension of Work.
What’s the Difference Between a Suspension of Work and a Constructive Change? For federal contractors, there are two main differences: . . .
No Special Defenses to Arbitration Agreements
Arbitration agreements, whether they are separate or part of a larger agreement, are contracts – an enforceable set of promises between parties. […]
How to Find (and Confirm) the Plain Meaning in a Contract
Contract formation confirms the parties understand and agree to all the essential terms. When that understanding and agreement fades, how do you […]
Navigating the Requirements for Claims against Virginia Public Entities
Contractors making claims against Virginia public entities must follow ALL applicable requirements. Such requirements may be found in several places, so check […]