Prime contractors, have you ever submitted a subcontractor’s claim to a public owner? Subcontractors, have you ever wanted to submit a claim against the government, but you had no contract with the government?
Generally, if the prime has or could have at least some liability (even potentially), then the prime can “pass-thru” the sub’s claim against the government.
A pass-thru claim will fail if the prime has severed or extinguished all liability for the claim between itself and its sub. This can be done by language that may already be in the subcontract or by a later agreement of release or settlement.
But, the same subcontract with the right language or a later agreement between the prime and sub (e.g., liquidation agreement) can preserve liability to keep a pass-thru claim alive.
A short success story:
A prime contractor on a project in Slick Rock, Colorado for the U.S. Dept. of Energy agreed to remediate uranium mill tailings. The prime submitted a pass-thru claim by one of its subcontractors against the Government (the Sub’s claim “passed-thru” the Prime to the Government).
The Government’s efforts to dismiss the claim failed because the prime had to pay whatever recovery it got from the Government to the sub. Only when the recovered amount (no matter how small) was paid, by the Government to the prime and then from the prime to the sub, was the prime’s liability extinguished. Until that point, the fire of the claim kept burning.
M.K. Ferguson Co., et al. v. U.S., Ct. Fed. Claims, No. 12-57C (April 14, 2016)
Acceptance and Intervening Cause Avoided Construction Warranty Claim
Like cars, computers, and appliances, construction projects include warranties too. Similarly, construction project warranties are limited to causes within the contractor’s control […]
Insurance Company Had No Duty to Defend Under Eight Corners Rule
To decide if an insurer has a duty to defend, a Virginia State or Federal Court may only look at the allegations in the complaint and the insurance policy to determine if a judgment against the insured will be covered by the policy.
Owner SOL When Mandatory Mediation Didn’t Toll Statute of Limitations
Contract interpretation strives to find the meaning of all parts together.
Government Must Review Claims in Good Faith, Not “Conjure Up” a “Baseless Retaliation”
A contracting officer’s review of certified claims submitted in good faith is not intended to be a negotiating game where the agency may deny meritorious claims to gain leverage over the contractor.
Termination for Convenience was OK to Get a Lower Price
When Massachusetts’ highest State court rejected Federal law on termination for convenience (T4C) a public entity’s “sole discretion . . . for […]
Pirates (Parties) Should Arbitrate Arbitrability
Yes, the word “pirates” is an anagram for “parties.” Participants in a lawsuit, arbitration, or mediation are collectively referred to as parties. Are they pirates too?
Very Bad Behavior Without Bad Faith is Not a Breach of Contract
Despite “abhorrent” behavior by the Army Corps of Engineers, a majority of the Armed Services Board of Contract Appeals held there was […]
Government Construction Contracts Require Bonds, Even When Contract Doesn’t Say So
Yesterday (Nov. 5, 2018), the Fed. Cir. Ct. of Appeals again endorsed the Christian doctrine, which can make unstated requirements part of a government contract.
Government’s Negligent Estimate a Trick?
The Government’s negligent estimate failed to provide the “most current information available.”