Prime contractors, have you ever submitted a subcontractor’s claim to a public owner? Subcontractors, have you ever wanted to submit a claim against the government, but you had no contract with the government?
Generally, if the prime has or could have at least some liability (even potentially), then the prime can “pass-thru” the sub’s claim against the government.
A pass-thru claim will fail if the prime has severed or extinguished all liability for the claim between itself and its sub. This can be done by language that may already be in the subcontract or by a later agreement of release or settlement.
But, the same subcontract with the right language or a later agreement between the prime and sub (e.g., liquidation agreement) can preserve liability to keep a pass-thru claim alive.
A short success story:
A prime contractor on a project in Slick Rock, Colorado for the U.S. Dept. of Energy agreed to remediate uranium mill tailings. The prime submitted a pass-thru claim by one of its subcontractors against the Government (the Sub’s claim “passed-thru” the Prime to the Government).
The Government’s efforts to dismiss the claim failed because the prime had to pay whatever recovery it got from the Government to the sub. Only when the recovered amount (no matter how small) was paid, by the Government to the prime and then from the prime to the sub, was the prime’s liability extinguished. Until that point, the fire of the claim kept burning.
M.K. Ferguson Co., et al. v. U.S., Ct. Fed. Claims, No. 12-57C (April 14, 2016)
Prime Contractor Had No Duty to Help Surety Investigate Sub’s Default
We all know what happens when we “ASS-U-ME” something. So, we should all carefully avoid assuming things unnecessarily.
It’s Good to Be the King
Mel Brooks in the movie History of the World: Part I (1981) said it best – “It’s good to be the King.” It’s also true when asserting claims against the State or an arm or agent of the State.
Smoke Without Fire: Damage from Concrete Dust Covered by Insurance
You’ve heard, “where there’s smoke, there’s fire.” In this instance, the smoke was concrete dust that damaged a warehouse full of aircraft […]
Changes Made After Substantial Completion Did Not Extend Overall Project Time
Contractors take heed – a time extension may be issued after substantial completion for specific work and the Government can still assess […]
One-Sided Construction Arbitration Clause Valid in Virginia
When it’s time to butt heads, know how the local turf (court) will interpret the clause.
Manage the Risk of Construction Changes
Almost any problem on a construction project can be traced to one of two things: changes or delays (even delays are really just changes). As in life, embrace and manage the change don’t run from it.
Want Your Profit? Prove a Constructive Change, Not a Suspension of Work.
What’s the Difference Between a Suspension of Work and a Constructive Change? For federal contractors, there are two main differences: . . .
No Special Defenses to Arbitration Agreements
Arbitration agreements, whether they are separate or part of a larger agreement, are contracts – an enforceable set of promises between parties. […]
How to Find (and Confirm) the Plain Meaning in a Contract
Contract formation confirms the parties understand and agree to all the essential terms. When that understanding and agreement fades, how do you […]