This applies to general contractors, subcontractors, and suppliers. Each can be the party preparing and transmitting a form of purchase order or (sub)contract or the party receiving the form and obligated to respond timely with agreement/performance or disagreement.
This happens every single day when a typical negotiation begins with a proposal, estimate, or bid from one party to the other. Next, an oral or informal written discussion occurs between the parties and terms are orally or informally agreed. At this point, the proposal, estimate, or bid may be marked-up. But, the negotiation is often not over and the agreement is not yet final.
After the proposal is marked-up, one party transmits a written P.O. or (sub)contract to the other. The proposal terms are not identical to the P.O. terms or (sub)contract. Among businesses, the receiving party must review and respond within ten (10) days. Failure by the receiving party to respond or commencing performance generally obligates the receiving party to the P.O. or (sub)contract terms.
The point is: review what you receive and make sure you agree or notify the other party that you disagree before beginning performance. Otherwise, you are probably bound to the terms of the other party’s form, which you did not write or prepare and which are probably not in your favor.
In the case of U.S. f/u/b/o San Benito Supply v. KISAQ-RQ 8A 2 JV, (U.S. Dist. Ct., N.D. California, Jan. 28, 2015), the lower-tier supplier was bound to the subcontractor’s purchase order when the supplier failed to disagree. In that case, the supplier was obligated to provide a mix design for 6000 psi concrete for a USACOE project at Fort Hunter Liggett in California.
The supplier’s proposal included the statement, “Quality Assurance program by others.” By this statement, the supplier argued the subcontractor was obligated to ensure the mix design was adequate. (The specifications were for performance, not design.) However, the subcontractor’s purchase order (the later document in the negotiation) included no such language. Although the supplier never signed and returned the subcontractor’s purchase order, the supplier did not inform the subcontractor of its disagreement instead commencing performance.
What began as the supplier’s Miller Act Claim for non-payment ended with the supplier paying for its defective concrete mix design, which was discovered after placement.
Government Must Review Claims in Good Faith, Not “Conjure Up” a “Baseless Retaliation”
A contracting officer’s review of certified claims submitted in good faith is not intended to be a negotiating game where the agency may deny meritorious claims to gain leverage over the contractor.
Termination for Convenience was OK to Get a Lower Price
When Massachusetts’ highest State court rejected Federal law on termination for convenience (T4C) a public entity’s “sole discretion . . . for […]
Pirates (Parties) Should Arbitrate Arbitrability
Yes, the word “pirates” is an anagram for “parties.” Participants in a lawsuit, arbitration, or mediation are collectively referred to as parties. Are they pirates too?
Very Bad Behavior Without Bad Faith is Not a Breach of Contract
Despite “abhorrent” behavior by the Army Corps of Engineers, a majority of the Armed Services Board of Contract Appeals held there was […]
Government Construction Contracts Require Bonds, Even When Contract Doesn’t Say So
Yesterday (Nov. 5, 2018), the Fed. Cir. Ct. of Appeals again endorsed the Christian doctrine, which can make unstated requirements part of a government contract.
Government’s Negligent Estimate a Trick?
The Government’s negligent estimate failed to provide the “most current information available.”
Prime Contractor Had No Duty to Help Surety Investigate Sub’s Default
We all know what happens when we “ASS-U-ME” something. So, we should all carefully avoid assuming things unnecessarily.
It’s Good to Be the King
Mel Brooks in the movie History of the World: Part I (1981) said it best – “It’s good to be the King.” It’s also true when asserting claims against the State or an arm or agent of the State.
Smoke Without Fire: Damage from Concrete Dust Covered by Insurance
You’ve heard, “where there’s smoke, there’s fire.” In this instance, the smoke was concrete dust that damaged a warehouse full of aircraft […]