Mediation is often a good idea, but only if it is “ripe.” An unripe mediation can leave a bad taste in your mouth. Have you ever tasted an unripe persimmon? Not only will it drain all the moisture from your mouth, but you may never want to try one again – the tannins of the unripe fruit are very bitter. However, having tasted one ripened to perfection, you will certainly want more. The same is true of most fruit and of your experience with mediation.
Assuming your construction contract includes a mediation provision and you just received a letter from a subcontractor requesting mediation, how should you respond? Since the contract obligates you to mediate, you should agree, right? Yes, but the contract and the request may not account for a pre-mediation exchange of information to ripen the dispute before a mediation session. Mediating without a reasonable understanding of each party’s position and the relative risks and rewards of settlement is like tasting an unripe persimmon – it will drain the good perspective that you had for mediation and you may never want to mediate again.
But how will a pre-mediation exchange of information succeed? After all, the dispute probably arose because the parties couldn’t or wouldn’t work together through normal project procedures? How then can the parties expect to ripen the dispute for mediation?
With time, the gradual exchange of information, a willingness to consider both giving and taking, and maybe the help of a third-party, the parties will understand that resolving the dispute now will likely save time and money later.
Acceptance and Intervening Cause Avoided Construction Warranty Claim
Like cars, computers, and appliances, construction projects include warranties too. Similarly, construction project warranties are limited to causes within the contractor’s control […]
Insurance Company Had No Duty to Defend Under Eight Corners Rule
To decide if an insurer has a duty to defend, a Virginia State or Federal Court may only look at the allegations in the complaint and the insurance policy to determine if a judgment against the insured will be covered by the policy.
Owner SOL When Mandatory Mediation Didn’t Toll Statute of Limitations
Contract interpretation strives to find the meaning of all parts together.
Government Must Review Claims in Good Faith, Not “Conjure Up” a “Baseless Retaliation”
A contracting officer’s review of certified claims submitted in good faith is not intended to be a negotiating game where the agency may deny meritorious claims to gain leverage over the contractor.
Termination for Convenience was OK to Get a Lower Price
When Massachusetts’ highest State court rejected Federal law on termination for convenience (T4C) a public entity’s “sole discretion . . . for […]
Pirates (Parties) Should Arbitrate Arbitrability
Yes, the word “pirates” is an anagram for “parties.” Participants in a lawsuit, arbitration, or mediation are collectively referred to as parties. Are they pirates too?
Very Bad Behavior Without Bad Faith is Not a Breach of Contract
Despite “abhorrent” behavior by the Army Corps of Engineers, a majority of the Armed Services Board of Contract Appeals held there was […]
Government Construction Contracts Require Bonds, Even When Contract Doesn’t Say So
Yesterday (Nov. 5, 2018), the Fed. Cir. Ct. of Appeals again endorsed the Christian doctrine, which can make unstated requirements part of a government contract.
Government’s Negligent Estimate a Trick?
The Government’s negligent estimate failed to provide the “most current information available.”