CAUGHT IN THE MIDDLE
New Mexico bridge case highlights the importance of written agreements for changes and delay compensation

In construction contracting, hope for (and focus on) the best after planning for the worst.

In 2018, the New Mexico Department of Transportation (NMDOT) selected a prime contractor for construction of a bridge in Quay County, N.M. (The eastern border of Quay County is also the New Mexico/Texas border). The prime subcontracted for cast-in-place piers and other bridge components. NMDOT and the prime entered into a change order to alter the pier design, which increased the quantity of work and delayed the project. Continue reading.

Published On: August 26, 2025

Share This Story, Choose Your Platform!

It’s Good to Be the King

October 16, 2018|

Mel Brooks in the movie History of the World: Part I (1981) said it best – “It’s good to be the King.”  It’s also true when asserting claims against the State or an arm or agent of the State.

Manage the Risk of Construction Changes

August 15, 2018|

Almost any problem on a construction project can be traced to one of two things: changes or delays (even delays are really just changes).  As in life, embrace and manage the change don’t run from it.

Share This Story, Choose Your Platform!

Jonathan J. Straw
Best Lawyers® - Jonathan Straw | 2026

Share This Story, Choose Your Platform!