The White House has directed Agency heads to “terminate or modify . . . covered contracts.” With some exceptions, there are numerous potential contracts on the chopping block. What should contractors do?
Upon receipt of a unilateral modification, assess whether the cost or time will increase in unchanged areas. For example, deductive changes for certain work could increase costs for other work that must still be performed. If costs were increased because of deductive changes, then carefully consider submitting a request for equitable adjustment.
Upon receipt of a notice of complete termination for convenience, promptly stop incurring further costs and, within one year of the termination, present a reasonable and well-supported termination settlement proposal to the Government under FAR 52.249-2(e). Recoverable costs include:
1. Costs actually incurred;
2. Profit on the work actually done; and
3. Costs of preparing a termination settlement proposal.
Upon receipt of a notice of partial termination for convenience, promptly stop incurring costs related to the terminated portion of the work and present a request for equitable adjustment within 90 days of the notice under FAR 52.249-2(l).
HEADER PHOTO: Termination by Nick Youngson CC BY-SA 3.0 Alpha Stock Images
Show Me the Money!
You told the guy to do the work, the work is done, and now it’s time for payment, right? But, you only told […]
Reasonable ≠ Ratio
“Circuit court litigation comes at a price, sometimes a heavy price.”
Words Matter
Remember the adage, “what you say today could bite you tomorrow.”
Recently, a Contractor won its argument before the Armed Services Board of […]
Run Through the Base, Not To the Base
Run Through the Base, Not To the Base
Thankfully, baseball season is back. While listening to a broadcast of my favorite team yesterday, […]
Having Your Cake and Eating It Too: Attorneys Fees Without a Contract Clause
How often have you wanted to take a dispute “to the mattresses” (think, The Godfather), but the cost was prohibitive? You have […]
Choose Your Own Venue: Where to File a Miller Act Lawsuit
Do you remember the Choose Your Own Adventure books? If you are a subcontractor on a federal project, where should you […]
Speak Now or Pay Later
This applies to general contractors, subcontractors, and suppliers. Each can be the party preparing and transmitting a form of purchase order or […]
General Contractors Waive Goodbye
General Contractors: When was the last time a private owner asked you to waive your lien rights before you did any work? […]
Unripe Mediation Can Be Bitter
Ripen the dispute for mediation with a gradual exchange of information over time.